Case Study – Architect’s Adjudication

In December, Bradbury Legal acted for a Queensland architecture firm in preparing an adjudication application against a builder for unpaid payment claims and variations claims. The architect was engaged to design an aged care facility in the New South Wales area. The builder sought to withhold over $200,000 from our client’s payment claim, citing back charges, defects, and unapproved variations.

In late October, our client submitted its payment claim for approximately $335,000. After issuing the section 17(2) notice, the builder certified just under $103,000, a difference of over $200,000. The Adjudication Application involved numerous late nights (including an all-nighter by Vinesh, Frankie, and Lachy), reviewing various documents, and drafting submissions and statutory declarations so that the Adjudication Application would be served before the Christmas shutdown period. In the end, the Adjudication Application totaled six folders worth of documents substantiating our client’s right to payment. This was a phenomenal effort by the Bradbury Legal team given the quantity of documents involved, the complexity of the issues, and the strict timeframes under the Security of Payment Act.

The Adjudicator awarded an Adjudication Amount of over $240,000 in favour of our client, representing an incredible result which the client was incredibly thankful for. The Adjudication Amount represented more than double the scheduled amount by the builder, promoting greater cashflow for the architecture firm.

Bradbury Legal is highly experienced in preparing and responding to adjudication applications. If you or anyone you know is struggling to be paid from a head contractor or developer or you have received an adjudication application, please contact Bradbury Legal.

The West Gate Tunnel leads to arbitration

The D&C JV contractors on the West Gate Tunnel (Project), CPB Contractors and John Holland (Subcontractors), have won the first round in their dispute against Transurban (Project Co) over the presence of contaminated “PFAS” soil in the tunnel area and subsequent purported termination of their contract due to force majeure.

In Transurban WGT Co v CPB Contractors Pty Ltd [2020] VSC 476, Victorian Supreme Court (VSC) refused applications designed to prevent the disputes from proceeding through arbitration.

Facts

The Subcontractors purported to terminate their contract with Project Co on 28 January 2020 due to the discovery and persistence of “PFAS” contamination, which it claimed was a “Force Majeure Termination Event” under the contract.[1] Since this time, the Subcontractors and Project Co have been engaged in disputes on the validity of the termination and various related matters.

By notice dated 2 March 2020, the Subcontractors sought to initiate a “downstream” arbitration with Project Co in relation to various claims.[2] Some 3 months later, Project Co initiated its own “upstream” arbitration in relation to various claims which it had passed upstream via its head contract with the State of Victoria.[3]

Project Co claimed the disputes were “Linked Disputes” under the contract with the Subcontractors. Project Co argued that clause 44A.3(a)(ii) operated to suspend the downstream arbitration while the upstream arbitration progressed (suspension clause).[4]

The Subcontractors sought to refer their various disputes with Project Co to arbitration. Project Co made an application for:

  1. a declaration that the suspension clause was enforceable; and

 

  1. an interlocutory injunction to restrain the Subcontractors from taking steps to progress the downstream arbitration until such time as the upstream arbitration was determined.[5]

The Subcontractor argued that the arbitral tribunal should decide whether to grant such relief to Project Co, not the court. The Subcontractor pointed to ss 5, 8, 9 and 17J of the CAAs which provide only limited powers for court intervention.[6]

The Subcontractor made a referral application to the VSC relying on s 5 and / or 8 of the Commercial Arbitration Act 2011 (Vic) (CAA), requesting the court refer Project Co’s query in relation to the operation of the suspension clause to the arbitral tribunal.[7]

Decision

Lyons J:

  1. found that the court had no power to make a declaration of the kind sought by Project Co;

 

  1. refused Project Co’s application for interlocutory injunctions; and

 

  1. granted the Subcontractor’s application to refer to the arbitral tribunal the question of whether the suspension clause was inoperative.[8]

Lyons J considered in detail the relevant law on the nature of arbitration and the limited ambit given to the court under the CAA. Some of His Honour’s key conclusions included that:

  1. the question whether the suspension clause is valid and enforceable was a matter ‘arising in connection with’ the contract between the parties and, therefore, it was a type of dispute the parties had agreed under their contract would be arbitrable;[9]

 

  1. the arbitral tribunal had the power to make orders relating to the validity, enforceability and/or applicability of the suspension clause of the kind sought by Project Co in court;[10]

 

  1. under the CAA the court’s power to grant interlocutory relief to matters which the CAAs apply derives from s 17J[11]. Accordingly, the court’s power to intervene is limited; and

 

  1. Project Co had failed to establish that the circumstances of the case were exceptional or objectively urgent such that court intervention was required.[12]

As a result, the Subcontractor’s claims in relation to the contract will be heard and determined by an arbitrator. The arbitrator will need to determine whether the suspension clause is enforceable and, if so, operates in the circumstances to pause the downstream arbitration.

Take Home Tip

Parties who agree to arbitration as their preferred dispute resolution forum should note that the courts are increasingly minded to allow arbitral tribunals to rule on their own jurisdiction or “competence” under the CAA. A party should closely consider whether their set of circumstances are truly urgent or exceptional to warrant intervention by the court. If not, it would be better to apply its resources in ventilating preliminary issues in the arbitration first, then challenging the arbitrator’s determination on those issues if necessary and as permitted by the CAA.

Importantly, Lyons J considered that he was bound by Hancock v Rhodes[13], being ‘a decision of an intermediate appellate court in circumstances applying sections of a uniform commercial arbitration act in force in each state in Australia.[14] This reinforces the relevance of the current decision of the VSC to parties in all States and Territories in Australia.

[1] At [10(1)].

[2] At [12].

[3] At [12].

[4] At [14].

[5] At [23].

[6] At [115] and [128].

[7] At [20].

[8] At [208].

[9] At [170].

[10] At [174].

[11] At [147] and [191].

[12] At [192] to [203].

[13] Hancock Prospecting Pty Ltd v DFD Rhodes Pty Ltd [2020] WASCA 77.

[14] At [147].

What is the amount of damages available to an owner for late completion of work on a residence that the owner does not intend to live in or rent?

In Leeda Projects Pty Ltd v Yun Zeng [2020] VSCA 192, the Victorian Court of Appeal (VSCA) was required to answer this question.

The case demonstrates that the court will look at the intention of the owner in ascribing a value, if any, to the use of the residence which was unable to be enjoyed as a result of a builder’s breach by late delivery of works.

Facts

In March 2011, Mrs Zeng and her husband purchased the penthouse of the Eureka Tower in Melbourne. On 24 September 2013, Mrs Zeng and Leeda Projects Pty Ltd (the builder) entered into a contract for fit out of the property as a private art gallery with a residential component consisting of two bedrooms with ensuites, a lounge, kitchen and laundry.

Mrs Zeng and her husband intended to use the property as a non-profit private art gallery and potentially spend some time residing in the property. They had access to several other Victorian premises to live in (when they were not travelling internationally), and their primary residence was in Shanghai. There was no intention to rent out the property.[1]

A dispute arose between the builder and Mrs Zeng. The builder made a claim to the Victorian Civil and Administrative Tribunal (VCAT) for progress payments and release of retention. Mrs Zeng counter-claimed for substantial damages on account of the delay in completing the works.

By the time the matter had reached the VSCA, it was not controversial that the builder had breached the contract as there was a delay period of 130 weeks between the date when the works should have been completed and the date when practical completion was achieved. Accordingly, Mrs Zeng was unable to occupy the apartment for those 130 weeks.

However, Mrs Zeng was not required to rent an alternative residence because she continued to live in Shanghai and had other Victorian residences available to her. Mrs Zeng did not lose:

  1. the opportunity to rent the property, as it was never intended to be a rental investment property; or
  2. takings from the art gallery, as it was intended to be a non-profit gallery.

Decision

The VCAT’s award of $100 nominal damages was not the correct measure, nor was the award of $357,500 plus interest by the trial judge for lost rental income at the rate of $2,750 per week.[2]

The VSCA[3] held that case authorities recognised the possibility of the loss of use of a property as being an available compensatory claim.[4] In ordinary cases, this might result in a financial loss to the owner of rent for an alternative residence.[5]

However, in this case, the proper award of damages to Mrs Zeng was $283,802.17 which Mrs Zeng spent on owners corporation charges, council rates and utilities during the 130 weeks.[6] These amounts were spent without benefit to her, but in respect of the property which the builder retained for its own use, being the completion of its works and were a reasonably foreseeable consequence of the breach of contract.[7]

Take Home Tip

If parties want to ensure certainty in the measure of damages payable by the builder in the event of delay, a mechanism for payment of a rate of liquidated damages for such a breach should be included in the contract. However, in doing so, parties must be mindful that a clause for liquidated damages may be challenged where the pre-estimated loss is found to be a penalty clause because it was not based on a genuine estimation of the loss that would result from the builder’s breach.[8]

In the absence of a liquidated damages clause, a builder faced with a claim should check whether the amount claimed is truly compensatory – i.e. does it put the owner in the position in which it would have been if the builder had not breached the obligation to complete on time?

[1] See [86] and [143].

[2] Per McLeish JA at [184].

[3] Comprised of Tate, Kaye and McLeish JJA. We note that McLeish JA gave the lead judgment on the ground dealt with in this case note, with Tate JA agreeing. Kaye JA agreed with the orders proposed by McLeish JA, yet His Honour gave a separate analysis of the authorities.

[4] Per McLeish JA at [174] and [175].

[5] Per McLeish JA at [179].

[6] Per Kaye J at [58] and McLeigh JA at [187].

[7] Per Kaye J at [57] and McLeish JA at [191].

[8] See Paciocco v Australia and New Zealand Banking Group Limited [2014] FCA 35.

ADR Processes Part II

This article is Part II of our article on ADR process. In this article, we will be covering the common pitfalls of ADR clauses. In Part I, we discussed the different types of ADR processes that are common in construction law matters. You can find Part I of our article HERE. While there are benefits to ADR processes, the drafting of dispute resolution clauses can sometimes result in the clause being void and unenforceable. Alternatively, there are times where the drafting of the dispute resolution clause means parties are left with a result under the contract which is unfair or unjust in the relevant circumstances. Often dispute resolution clauses are thrown into a contract without the parties giving much thought or consideration as to its enforceability or suitability to the circumstances. The following matters are pitfalls you should consider when you are drafting a dispute resolution clause.

 

Factors that may make the clause void and unenforceable:

 

Precondition to Court or other legal action

 

One of the biggest problems with ADR clauses arises when they set compliance with the ADR process as a pre-condition to seeking any court relief. This is problematic because it attempts to prevent the parties from approaching the Court when it has jurisdiction. If not properly drafted, these types of clauses can make the dispute resolution term unenforceable.

 

Words or phrases to look out for:

 

The parties must not seek any court orders until the parties have attended mediation.

 

Words or phrases that can prevent the clause being unenforceable:

 

Nothing in this clause X prevents the parties from seeking urgent or injunctive relief from the Court.

 

The key difference between these clauses is that the first tries to remove the jurisdiction of the Court by preventing the parties from seeking any relief from the Court until after the ADR processes have been complied with. This can result in some of the parties’ legal rights being wrongly enforced under the contract. For example, in cases where one party seeks to have recourse to security and the other party disputes this, the ADR process mechanisms may be too slow in resolving this dispute. Therefore, it is appropriate for the Court to be able to order urgent or injunctive relief to prevent recourse to the security. The parties can still have the underlying dispute proceed to the elected ADR process, but the security providing party may be able to (in the interim) prevent recourse where it is contested that the other party is not entitled to the benefit of that security.

 

Agreement to agree

 

A dispute resolution clause will be unenforceable if it is void for uncertainty. This often happens when there is an agreement to agree in a clause. For example, if a contract provides that the parties must agree on a matter and the parties are unable to reach an agreement, where do the parties stand in respect of their contractual duties? In the context of a dispute resolution clause, this can occur when the parties are required to agree on the form of the dispute process, or the appropriate body to determine the dispute or the rules that are to be applied to determine the dispute.

 

Words or phrases to look out for:

 

The parties must agree on an expert’ or ‘the parties must agree on the form of dispute process

 

Words or phrases that can prevent the clause being unenforceable:

 

The parties must agree on an expert. If the parties cannot agree, the expert shall be appointed or administered by the [for example] Australian Disputes Centre.’

 

The important difference between the two clauses is the second has a mechanism for resolving the uncertainty. If the parties cannot agree on which expert should be appointed, the clause provides for a third party to appoint or determine who the expert will be. Obviously, when nominating a third party to make the decision, it is important to confirm that the third party can and will appoint a dispute resolution professional.

 

Time frames should also be included as part of these clauses to avoid uncertainty. For example, a clause may state that parties are given 14 days to meet together to discuss the dispute before it proceeds to mediation. Without the 14 day timeframe, there is no clear indicator of when the parties are to engage in their dispute resolution process. A deeming mechanism should also be included to account for when the parties simply do not comply with the dispute resolution process. For instance, if the parties do not meet within 14 days, then the dispute should be automatically referred to mediation, or expert determination (as per the next tier of the agreed dispute resolution process) or simply allowed to proceed to litigation.

 

Broad and unclear drafting

 

The last pitfall of dispute resolution clauses discussed in this article is broad and/or unclear drafting. As a general problem with contracts, broad and/or unclear drafting can result in less certainty in the obligations between the parties. In the context of a dispute resolution clause, unclear drafting may occur in any of the following circumstances:

 

  • where there is not a clear process for a dispute to be resolved;
  • where the scope of the ADR powers and what can they determine is not defined;
  • where the rules that guide the ADR process are not clearly referenced; and
  • when can parties appeal the decision.

 

The consequence of broad and/or unclear drafting is that when a dispute arises, further disputes may occur when it comes time to interpret the clause. If a Court considers that the clause is uncertain and is unable to be properly interpreted, it may be held that the clause is void for uncertainty.

 

To assist with some of the considerations that arise with broad or unclear drafting, the next section of this article gives commentary on some of the considerations of ADR clauses so as to ensure your clause is suited to the parties and properly drafted.

 

Important Considerations in ADR clauses

 

Scope of ADR power

 

A dispute resolution clause can be customised by the parties. One way that parties can customise their dispute resolution clause is by determining what types of dispute will be resolved in which ways. For example, the parties may agree that technical matters to do with the scope of works or variations are unsuited to a determination by a legal professional. In such technical matters, the Courts will often have to consider expert reports from both parties, including any updates and responses from the experts. Even after considering the expert reports, the Court may nevertheless be unequipped or unsuitable to determine exactly what the correct outcome is or should be. Methods such as expert appraisal or expert determination can be effective ways of the parties reducing their costs and ensuring an appropriate resolution of the dispute. If this method is agreed by the parties, it is important to clearly set out exactly which disputes are to be resolved in which way. For example, the dispute resolution clause may state that any dispute involving a disputed variation or defective work that hinges on a technical interpretation must be resolved through expert determination. Accordingly, such a clause would also express that any dispute that hinges on legal interpretation be directed to a court of competent jurisdiction.

 

Statutory Provisions

 

When drafting a dispute resolution clause, it is important to consider whether there are any statutory provisions that may impact on the operation of the clause. For example, the Home Building Act 1989 (NSW) prevents the use of arbitration in some contracts for residential building work. In Victoria, the Building and Construction Industry Security of Payment Act 2002 (VIC) has an intricate regime for claimable variations in high value contracts (being contracts with a consideration over $5,000,000). These statutory provisions can have significant impacts on the clauses chosen by the parties. Further, while the Home Building Act prohibits the use of arbitration, the Victorian Security of Payment Act has consequences for the parties depending on the type of resolution used. It is important then to consider the statutory provisions and what their effects may be.

 

Binding or non-binding

 

A major consideration that parties should think about is whether to have the dispute resolution process as a binding or non-binding method. The Courts have generally held that where parties agree to a binding dispute resolution process, they will be unable to appeal the determination. While there may be circumstances where the parties can appeal to have the determination overturned, as a general rule, parties should expect to be bound by the decision. Therefore, parties should consider when they want to be bound by the decision of the dispute resolution professional.

 

Rights of appeal

 

While the process may be binding, the parties may agree to allow for appeal rights in the dispute resolution clause. For example, the parties may agree that a decision can be appealed where a party claims there has been a manifest error of law or where the amount in dispute exceeds a specified threshold. These mechanisms are interesting ways that parties can customise their dispute process and ensure that they are satisfied with the way any potential disputes will play out. It is important to consider any cost implications with appeal rights. While parties may not wish to be bound by a decision in certain circumstances, appeal rights may inevitably lead to higher costs in resolving a dispute.

 

 

Coronavirus (COVID-19) and Construction Contracts: What are your options?

Coronavirus (COVID19) and the construction industry: What are your options?

We recently published an article about how construction contracts can incorporate concepts of force majeure events. A copy of our article can be found here.

As the disruptions of corona virus begin to become more extensive with government mandates coming into effect, we believe it’s important for those in the construction industry to have a quick reference guide as to their options or important things to think about.

 

Pre-contract: Tendering, negotiating and drafting of contract
Force Majeure clause ·         Manages the relationship between the parties where there has been an ‘Act of God’ or other similar severely disrupting event

·         Depends on the contractual definition of the term

·         Generally, suspends the obligations until the force majeure event has concludes

·         Important to consider when the parties’ obligations will resume – what will indicate the end of the force majeure event

Scope of Works and mitigation of supply chain risk ·         Where possible, alternative supply or materials should be specified in the scope of works with pre-agreed variation prices
Extensions of Time ·         Can include force majeure event as a qualifying cause of delay

·         What circumstances can the contractor or subcontractor seek an EOT?

·         Generally appropriate for an EOT to be granted where there is suspension of works, variation, act, omission or breach of the other party, force majeure events and/or industrial action occurring across the relevant state or territory

·         Are there any duties to mitigate the delay which are a precondition to receiving an EOT

Delay Costs and/or damages ·         Does the contract provide for any delay costs or damages?

·         What are the circumstances that the contractor or subcontractor is entitled to costs and are there any relevant caps?

Legislative Provisions ·         How are the change in legislative requirement provisions worded?

·         Consider the definition of legislative requirement (and/or equivalent and related definitions)

·         Consider whether legislative provisions should include a carve out for where there is a change in the legislative requirements in relation to COVID19. Given the uncertainty around how the government will proceed, it is difficult to predict how the legislative regimes or executive orders will change as the response to COVID changes and adapts

Labour and Key Personnel ·         Are there any key personnel of the contractor or the subcontractor that should be specifically identified?

·         Are there specific measures the Principal/Contractor want to specifically implement? Examples may include split teams

Security ·         Consider what types of security will protect against insolvency risk of contractors or subcontractors – Parent guarantee, retention monies, material security and/or bank guarantees

·         Consider circumstances where there may be recourse to the security such as where a party becomes insolvent or there are defective works that require rectification

·         Consider Principal security for payment if there are any solvency concerns

Insurance ·         Principals should consider whether there are suitable insurance policies to protect from any delays to the works or any consequences that the delays may have at the end of the project

·         For example, Principals may wish to discuss delay in start-up insurance with their insurance broker

Warranty deeds and defects ·         Principals may wish to require warranty deeds from the subcontractors to insure against any insolvency risk from contractors and to allow for any defects to be rectified independent of the contractor
Financial capacity of the tenders ·         When assessing potential contractors, Principals should consider the financial capacity of contractors and whether there are any solvency concerns and if there are any parent companies that can provide guarantees
Project deadlines ·         What deadlines are imposed by related contracts such as sale of land for off the plan properties

·         How long are the deadlines and timeframes of the project? Can they be extended to account for coronavirus

Contract structures ·         Profit/cost-saving sharing models of contract or guaranteed maximum price may be considered by Principals to minimise cost exposure of contracts that may be affected by coronavirus (such as supply chain risk)
Contract administration
Extension of time ·         Principals and Superintendents generally have the power to issue an EOT even when a claim may not be made by the Contractor. While they are not obliged to use this power for the benefit of the contractor, there may be practical and goodwill benefits in using these powers

·         Contractors should seek legal advice in terms of the relevant EOT clause and whether they have a right to seek an EOT or what other options are available to them under the contract

Suspension ·         Suspension is generally a grounds for an EOT

·         Consider who bears the cost of suspension under the contract

·         Is there a right for the contractor to claim any suspension costs or costs associated

Change to legislative requirements ·         In the event of government mandated shutdown, there is likely going to be claims for legislative changes. These will largely depend on the wording of the clauses, who bears the risk on legislative changes and the form of the government shut down

·         Other considerations include whether construction work is considered an essential service and to what extent

Variations ·         Where there is a supply chain breakdown due to closed borders, there may be claims for variations being made by Principals or Contractors to allow the project to continue

·         Variations will be linked to the scope of work and whether there are alternatives that can be sourced

Payments ·         Principals may wish to change payment terms to accommodate contractors or subcontractors

·         As the effects of coronavirus move throughout the economy, there will undoubtedly be businesses that struggle and become insolvent. Where possible, Principals may want to consider changing milestone payments or frequency of payment claims to assist contractors’ cashflows

·         Any agreement between the Principal and relevant contractor should be evidenced in writing

Acceleration ·         If there is relatively small amount of work left, Principals may consider giving directions to accelerate

·         While this may increase the cost of the project, the Principal may be able to ensure the project is completed before shutdowns come into effect

Employment ·         Employment law advice should be sought about how to manage employee relationships while projects are on hold by reason of coronavirus
Teams and social distancing ·         Head contractors may wish to implement policies that flow down the contracting chain in relation to splitting teams and social distancing where possible
Other arrangements agreed between the parties ·         Sometimes the best changes are those made between the parties and not from the lawyers

·         However, even where this is the case, ensure that such agreements are evidenced in writing and you seek legal advice on the impacts of the agreement and whether there are any potential consequences that you may not have considered

Other issues
Financiers ·         In many developments, there may be a financier involved and different obligations that arise under these loans and security documents

·         Principals should consider their obligations to notify their financier(s) where appropriate

Other stakeholders ·         There may be a range of other stakeholders that may have an interest in the construction contracts

·         It is important to manage these aspects of the development to reduce or eliminate any potential problems later on

Dispute resolution
SOPA claims ·         At the time of writing, there have been no changes to the strict deadlines imposed on submitting and responding to payment claims under the NSW Security of Payment legislation

·         SOPA is a contractor friendly forum, allowing for money to flow down the contracting chain

·         SOPA claims can be challenged on jurisdictional grounds or can be settled at the end of the contract if there has been an overpayment

Alternative dispute resolutions ·         Many alternative dispute resolution professionals are not taking new appointments. This can create a delay in parties complying with the relevant dispute resolution clauses

·         Parties may consider teleconferences or videoconferences to resolve disputes, rather than physically meeting

Courts ·         Many courts are operating via videoconferencing, with physical appearances limited

·         The court process may have more delays than usual as judges and parties adjust to the temporary measures of case management

·         Where a party is seeking urgent injunctive or other relief, it is important to seek legal advice as soon as possible to ensure that an application can be made efficiently and protect your interests

Contract termination ·         If you are seeking to terminate the contract it is important to terminate in accordance with the contractual provisions and to consider any common law rights or duties in relation to termination

·         Those seeking to terminate where the counterparty has become insolvent will also need to be aware of the recent insolvency changes and the restrictions on terminating pursuant to insolvency

 

 

ADR Processes

 

ADR Processes: What are they and how do they work?

 

In many construction contracts, it is common to have a clause that deals with the process the parties will go through if a dispute arises. These clauses attempt to provide an alternative dispute resolution (ADR) process to litigating over every dispute that arises. While there are some disputes that are suited to being litigated (such as where a specific legal remedy is needed, the subject matter involves the legal rights of the parties or the issues are legally complex), many can be resolved through an ADR processes. ADR processes, if effective, can reduce the time and cost of disputes for parties.

 

This article discusses the different types of ADR processes and Part II will address some of the common pitfalls of ADR clauses that render these clauses unenforceable.

 

Types of ADR processes:

 

When it comes to construction disputes, there are several standard types of ADR processes. These include:

 

  • Negotiations between senior executives or authorised representatives;
  • Mediation;
  • Arbitration; and
  • Expert determination and appraisal.

 

Negotiations

 

Negotiation between senior executives is the most simple and informal dispute resolution process. The senior executives or authorised representatives meet and discuss the dispute that has arisen. Using their best endeavours, the authorised representatives can talk about how the dispute may be resolved and attempt and find any potential compromises. While the discussions may not necessarily resolve the dispute, it gives the parties a chance to hear the other side and understand the issues faced by the other party. This can help narrow the issues that are in dispute between the parties, saving significant time and money if the dispute escalates to litigation.

 

Mediation

 

The next step in the ADR ladder is mediation. Mediation is slightly more formal than negotiations between the parties’ authorised or senior representatives. This is because mediation involves appointing a third party (the mediator) to meet with the parties and work to resolve the dispute. The mediator will discuss the positions and interests of each party and try to find common ground on which the parties can agree and tries to help facilitate a resolution of the dispute.

 

One of the biggest benefits of mediation is the fact that it is so flexible in the resolutions that can be generated in response to a dispute. For instance, parties can find creative or unorthodox solutions to their problems which would not be available if the dispute were to be litigated. At mediation, the parties have the control over the resolution of the dispute and can work together to create a solution that is potentially more appropriate than a court order.

Arbitration

 

Arbitration is a common dispute resolution process in the building industry. Between commercial parties, arbitration can be an effective alternative to court because it operates much like a Court. The Commercial Arbitration Act 2010 (NSW) sets out the various matters relating to domestic commercial arbitrations including the arbitrator’s powers and the appeal process. The decisions of arbitrators are binding and the resulting awards can be enforced by the Courts.

 

Arbitrations can sometimes be as expensive and time consuming as litigation. This is because of several factors such as the cost of hiring an arbitrator and decisions are often appealed. However, some of the benefits of choosing arbitration include that it can be confidential and allows the parties to have more control over the rules and procedures that resolve the dispute. Subject to any overriding arbitration legislation or rules, the parties can essentially decide how they want the determination to run, how many arbitrators they want involved or any grounds of appeal.

 

Expert Determination

 

Another ADR process discussed in this article is expert determination. Expert determination can be binding, or non-binding (dependent on the rules of the particular expert agreement or contract that sends the parties in dispute into that forum). Unlike arbitration, there is no statutory framework for expert determination or appraisal. Therefore, it is the contract that will guide the expert and their decision. Using an expert to make a final and binding decision is useful, as the majority (if not all) building disputes will rely on expert evidence to determine issues such as program, defects or rectification costs.

 

Using non-binding expert determination can prevent or reduce the need for a court to consider these technical issues and can simplify the litigation process. A potential drawback for expert determination is that it can be very difficult to challenge. Provided the expert has understood the scope of their obligations and the issues they need to review, it often will not matter if the expert made a mistake, a gross over or under valuing or if irrelevant considerations were considered. As stated by the NSW Supreme Court in TX Australia Pty Limited v Broadcast Australia Pty Limited [2012], the fundamental question is whether the exercise performed by the expert in fact satisfies the terms of the contract.

 

It is not uncommon for a dispute resolution clause to have multiple different ADR processes available to the parties. For example, parties may be required to enter negotiations with each other and then must proceed to mediation or arbitration. Therefore, it is important to understand the aspects of each different ADR process so that you can choose the one most appropriate for your business. Each ADR process has its benefits and its drawbacks and will be more effective for certain types of disputes. In the Part II of this article, we will look at dome of the common pitfalls of ADR clauses. Particularly, how you ensure that the clause is enforceable, the key aspects of the ADR clause, and what are the common issues that arise when negotiating an ADR clause.

Expertly building evidence: Lessons learned from White Constructions

Case note: White Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166

In White Constructions, Hammerschlag J considered the issue of delay damages. White Constructions was the property developer of a site in Kiama NSW. The development involved the development and subdivision of 100 lots and required design and installation of sewer infrastructure. These works required a s 73 Certificate issued by Sydney Water before subdivision could occur. White Constructions appointed the Defendants to assist with the design and approval works needed as part of the development and resulting subdivision. A substantial part of the judgment was devoted to the preparing and designing of the sewer designs and the approval of Sydney Water, including the different types of sewage systems, Sydney Water’s preference in relation to these systems, preparation of option reports and correspondence between the Superintendent, the Defendants and Sydney Water.

The discussions between Sydney Water, the Superintendent and the Defendants took considerable time. As a result, White Constructions alleged that the delay in coming to the approved sewage design caused White Constructions to be liable to their building contractor for delay damages. In arguing the substance of the dispute, the parties tendered complex expert evidence. As a result, the Court appointed an expert to assist in interpreting and assessing the expert evidence presented.

With the expert’s assistance, Hammerschlag J criticised the experts’ approach to determining the delays attributable to the sewage works. Both experts used methods derived from the United Kingdom Society of Construction Law, the Delay and Disruption Protocol (the Protocol) in analysing the delay. The Protocol identifies six different methods of delay analysis, but Hammerschlag J held that the inclusion of a delay analysis method in the Protocol does not necessarily mean it should be used. While the Protocol methods have been endorsed in other cases, the analysis of delay must pay close attention to the actual evidence of what was happening on the ground of the project. The delay analysis must show and prove that, on the balance of probabilities, the delay:
• played a role in delaying the project;
• how it delayed the project; and
• how much it delayed the project.

This approach is in line with the common law common-sense approach to causation which the High Court referred to in March v E&MH Stramare Pty Ltd (1991) 171 CLR 506.

A lot of value in White Constructions comes from Hammerschlag J’s analysis of what evidence is needed in cases where delay is alleged in construction matters. Firstly, the Court stated that close attention must be paid to the facts of the matter, rather than the opinion of experts. This evidence should not be general in nature, but specific in that it is able to precisely identify delays in the project. This evidence should be a contemporaneous record of the project. A classic example of this kind of evidence is a site diary which records the day to day of the project, as well as specific cause and effect of each delay.
• what works were undertaken/completed;
• the instructions received from the client;
• the delays/any complaints of delays and how they have affected other activities;
• which personnel were onsite; and
• any other relevant details

The Court found that it was important that the contemporaneous record identified which activities were adversely affected by the delays. For example, if the works of one contractor were delayed and, as a result, caused delay for another contractor, the site diary should record these details. Failing to record these details means that it is harder, if not near impossible, for parties to establish that there was in fact a causal link and adverse effect.

How does White Constructions impact a project?

White Constructions shows the importance of proper project documentation. Most importantly, the site diary, or similar contemporaneous document, should be the primary record of the specific of what is happening on site and how specific events affect different contractors. Proper record keeping, while it may be administratively burdensome, allows the Court to analyse and determine the proper entitlements of the parties if the project ever comes into dispute. While other evidence can be adduced in pursuit of proving delay, it runs the risk of being generalist in nature and not enough to prove the causal link of the delays.

The lessons learned in White Constructions may also have some application in respect of other delay related mechanisms under construction contracts. For example, a comprehensive site diary would also be useful in determining any claim for an EOT claim. However, it is important to note that these types of claims are largely determined by the contract and its processes for determining what is in fact an EOT. Nevertheless, contemporaneous records of what has happened and how this has affected the project is useful in establishing a claim by a party as to their entitlements.
Another important point that comes from White Constructions is ensuring experts are given the proper lay evidence to ensure that they can properly opine on the project. While it does not displace the role of lay evidence such as site diaries, it can assist in assisting the Court in considering and making appropriate decisions on what the parties are entitled to.

If you or someone you know wants more information or needs help or advice, please contact us on +61 2 9248 3450 or email [email protected].

Different options for resolving building disputes

A building dispute can have serious implications for all parties involved, the most obvious being delays to the construction project and the resulting financial loss.

A dispute may arise from disagreements over the interpretation of a contract term, incomplete or defective works, variations to the scope of works, or charges for prime cost items and provisional sums.

Bringing a building dispute matter before a court or tribunal can exacerbate the issues between the parties, delay the project further, incur additional costs and cause even more damage to the parties’ strained relationship. It is almost always beneficial to settle a building dispute through alternative dispute resolution (ADR).

ADR involves retaining an impartial third party to assist in reaching an early settlement of the matter. In fact, most jurisdictions require that parties to a building dispute make genuine attempts to settle the matter before proceeding to a tribunal or court.

Construction contracts often contain ADR clauses that specify the approach to be used if a dispute arises. The ADR method may be facilitative, advisory or determinative.

When preparing or entering a construction contract, it is important to understand the different ADR approaches and their implications, and to choose the type most suited to the circumstances. If there is no ADR clause, the parties may agree to use a particular method. The following is a summary of each.

Facilitative

A building dispute may be resolved through mediation which involves a neutral person meeting face to face with the parties to assist them in narrowing the disputed issues, exploring options and reaching a solution.

Mediation is informal and confidential, and the mediator does not provide legal advice nor does he or she determine the matter. The parties should be willing to negotiate in good faith and make genuine attempts to resolve the dispute.

The parties meet in a “without prejudice” environment and the mediator coaches the parties through the issues and encourages them to engage in meaningful negotiations.

Mediation allows the parties to reach an early settlement that may be more flexible than one imposed by a court or tribunal and may assist in preserving the parties’ commercial relationship allowing them to continue working throughout the project and beyond.

The construction contract will usually specify who may be appointed as a mediator and stipulate who is responsible for the costs of the mediation – this is often shared equally between the parties.

Advisory

Advisory ADR processes may include conciliation, expert appraisal and case appraisal. Each involve the appointment of a third party to consider the available material and provide advice regarding the facts and appropriate law and how the matter may be settled.

Early Neutral Evaluation was first used in the United States in response to a critical backlog of cases within the courts system and generally falls within the category of case appraisal. An evaluator with knowledge of the law is appointed and considers the parties’ respective arguments and evidence. The evaluator may be a dispute resolution practitioner or judicial officer. They make a non-binding evaluation of the strengths and weaknesses of each side, the likely liability and an estimate of damages.

In other words, the parties are provided an expert opinion, from an experienced and respected neutral party, regarding the likely outcome if the matter was to go to a court or tribunal. The evaluation is confidential, and the appraisal provided generally encourages settlement without the delay, costs and formalities associated with a court or tribunal hearing.

Senior Executive Appraisal, also known as a mini-trial, involves a panel of senior experts joining an independent neutral third party to consider and evaluate the dispute. The parties present their own evidence and the panel convene to attempt to settle the matter. The power conferred on the panel and independent third-party is predetermined by agreement.

Determinative

An independent expert with appropriate technical knowledge is appointed by the parties to determine the dispute. The determination is generally made on the respective parties’ written submissions, statements and evidence and the expert may conduct his or her own investigations before determining an award. Oral evidence does not usually form part of the process.

The contract generally sets out the process governing this method of ADR, including who the expert should be, how the expert is appointed, the relevant timeframes, the binding nature of the decision and how costs are to be paid.

If the contract provides for the determination to be binding and a party refuses to comply with the decision, then the other party will generally need to rely on the contract’s provisions to enforce the decision through the court.

When ADR is unsuccessful

Not all building disputes may be successfully negotiated.

If resolution is impossible or impractical, either party may make the appropriate application to their state or territory Administrative Tribunal or court. The matter will proceed according to the type of construction project, the value of the claim, and the parties to the dispute. Tribunals and courts are formal jurisdictions and have strict processes and timeframes.

Conclusion

Unresolved building disputes can escalate quickly depleting valuable time and resources of the parties involved. Utilising ADR to resolve a dispute can be time efficient, cost effective and assist in preserving the relationship between the parties.

Determining which ADR method is appropriate will depend on the facts and circumstances of each case. In all matters however, the parties should be willing to listen and make genuine efforts to negotiate and resolve the issues.

If you or someone you know wants more information or needs help or advice, please contact us on +61 2 9248 3450 or email [email protected].

Fire in the sky: Lacrosse building consultants found liable for cladding

A Frenchman lights a midnight cigarette on his balcony in Melbourne. In less than three hours, most of the 23-storey high rise building catches fire. The Docklands area narrowly avoids burning to the ground.

Thanks to the incredible work of the fire brigade, the occupants and the sprinkler system, not a single one of the tower’s 400 occupants or anyone in the Docklands was hurt by the towering inferno.

Like Deep Purple’s rock classic, this is a true story, the butterfly effect of nightmares for three consultants to a building project. They were found, in what was crucially a breach of their consultancy agreements, to have contributed in various ways to the installation of combustible cladding on the building. This was against the regulations that applied to the high-rise.

They have been ordered by the Victorian Civil and Administrative Tribunal per His Honour Judge Woodward to foot a $5.75 million bill. More damages may follow. A further $6.8 million in claims is still being heard by the judge, mostly for removal and replacement of the unburnt cladding.

It was a landmark decision, one of the first in Australia on liability in relation to combustible cladding. It will not be the last. High rise building owners and building consultants must carefully examine their properties (and their contracts), or they could be next.

To see the full 227-page judgment, follow this link.

For the key details and what builders, consultants and residents need to know moving forward, keep reading.

The events

At about midnight on 24 November 2014, one of the Lacrosse residents returned from work and had a cigarette on a level 8 balcony. Leaving the almost-extinguished cigarette butt in a plastic tray, he went to bed.

Unfortunately, the tray contained aluminium foil, a plant and a packet of seeds. After two hours, everything combustible on the balcony caught alight, including the timber table, some clothes and an air conditioning unit. High-rise balcony areas are high-risk fire hazards.

The building was clad in aluminium composite panels (otherwise known as ACPs) which had a core containing the highly combustible material, polyethylene. Polyethylene has a combustibility similar to petrol and diesel. In the space of twelve minutes the fire spread from floor eight to floor twenty-one.

The use of an ACP with a 100 percent polyethylene core as part of the external wall of the building was found to be “primarily responsible” for spreading the fire.

The applicants

The 211 owners of the various floors and individual apartments brought the case. This included three owners corporations.

The respondents

The case was brought against eight respondents:

  • L U Simon Pty Ltd was the builder;
  • Stasi Galanos and his employer Gardner Group Pty Ltd, who was the building surveyor;
  • Elenberg Fraser Pty Ltd was the architect;
  • Tanah Merah Pty Ltd trading as Thomas Nicholas was the fire engineer;
  • the resident who lit the cigarette;
  • the primary occupier of the smoker’s apartment unit; and
  • the superintendent of the build, Property Development Solutions.

This was the cast of characters in Owners Corporation No.1 of PS613436T v LU Simon Builders Pty Ltd [2019] VCAT 286.

Liability of the builder

The builder’s warranties (promises) stated in the Victorian Domestic Building Contracts Act 1995 were the basis for its overall liability. It was alleged that the builder:

  • Had failed to provide materials good and suitable for the purpose for which they were used;
  • Had not carried out work in compliance with the Building Act 1993 (Victoria) and the Building Code of Australia (BCA), and
  • Had not used materials reasonably fit for a particular purpose which was stated in the contract, in circumstances where the building owner clearly relied on the builder’s skill and judgment.

Such warranties are a part of every domestic building contract, and very similar warranties are implied into many home building contracts in NSW law.

In this Victorian case, combustible panels were found to be not good or suitable for the purpose of being used as external walls of a high-rise residential building. The cladding did not avoid the spread of fire in the building so as to prevent injury and property damage. The builder had made an error in selecting these materials.

However this was not the end of the story, as “not every error is negligent” at law.

To be found negligent, the builder had to have failed to take reasonable care in selecting the ACPs. Judge Woodward found that the builder had not failed, for three reasons:

  1. The builder had not known that ACPs were highly combustible and was not expected (at least in 2011) to know this;
  2. The installation of ACPs was a part of the building contract itself, forming the annexed performance requirements; and
  3. The builder had signed consultancy agreements with “highly skilled professionals” (consultants) to supervise and ensure that the complex project was compliant with the BCA. By engaging them, the builder had relied on their expertise.

Liability of the consultants

Point (3) just above meant that there was a possibility that the consultants (the fire engineer, the building surveyor, and the architect) were responsible for the damage. It was alleged that these were the parties who had failed to exercise due care and skill in relation to the installation of the ACPs.

Judge Woodward agreed. Courtesy of the consultancy agreements, the builder was able to pass almost all of the risk in relation to the BCA compliance of the cladding down to the consultants. The consultants were ultimately at fault, and apportioned the $5.7 million in damages as follows:

  • The fire engineer was found liable for 39 percent of the damages;
  • The building surveyor was found 33 percent liable; and
  • The architect was found 25 percent liable.

The French smoker was found 3 percent liable, but given he did not appear in the proceedings and his responsibility was found to be “minimal’ by the judge, the builder copped this amount instead.

Each judgment was made considering the particular consultancy agreement between the consultant and the builder.

The fire engineer: 39 percent liable

As the “primary consultant responsible for fire safety compliance”, the fire engineer was always going to be in trouble.

It had failed to conduct a full fire engineering assessment that would inquire into and assess the range of construction materials. The purpose of this assessment was to identify potential fire hazards of the building.

The fire engineer made the almost-deadly error of assuming that it was not required to conduct an assessment under the consultancy agreement that it had signed. This was incorrect. It was in fact required to conduct some proactive investigation and assessment of the building materials, which it did not do.

It had also failed to warn the builder (and also the other consultants) that the ACPs used for the high-rise residential building did not comply with the Building Code of Australia. Finally, it had also failed to advise about a solution to the non-compliance.

The fire engineer was found the most liable out of everyone, for the simple reason that it was the only professional on the project who actually knew that ACPs were not compliant and were fire risks. A simple email or comment at a meeting may have got it out of trouble. Its inaction was costly.

The building surveyor: 33 percent liable

The builder surveyor was in the firing line primarily because it had decided to issue a Stage 7 Building Permit. Through this, ACPs were approved for use on the façade of the building despite not being in compliance with the BCA. This was allegedly a breach of its consultancy agreement.

However, it was also alleged that the building surveyor’ failed to query the incomplete description of the cladding systems in the fire engineering report, and also that it failed to properly inspect the work during construction for compliance with the BCA.

Judge Woodward found that, notwithstanding some expert evidence to the contrary, the building surveyor’s had failed to give adequate consideration to whether the ACP was compliant with the BCA before issuing the permit.

The building surveyors might have had a defence if the builder did not give them insufficient information about the materials used in construction. Unfortunately for the Lacrosse tower building surveyors, this was not the case.

The architect: 25 percent liable

The other consultant in hot water was the architect.

The allegation was that the architect had made an agreement to prepare architectural drawings of the external cladding that satisfied legislative requirements, and it had breached this agreement. The allegation was also that it had failed to check whether the sample of the ACP provided to it complied with the BCA and was fit for purpose.

Both allegations were proven. The design specified ACPs for the external walls of the tower, including one with 100% polyethylene core, which was a breach of the BCA. Secondly, as head design consultant, it was also responsible for ensuring that the ACP sample it provided was compliant with its design intent and the BCA. In approving of a sample of the ACP, it had failed to exercise due care and skill.

Overall

In summary, the consultancy agreements between the builder and the consultants existed for the commercial purpose of ensuring ongoing involvement from consultants in the project, and therefore ongoing responsibility for the work.

Judge Woodward found that the involvement of the consultants, on terms that they would advise on non-compliance of building materials, meant that they and not the builder were liable for the fire damage.

The lesson for consultants: know exactly your obligations under a contract, whether they are immediate or over a longer period of time, and warn of non-compliances with the law consistent with your knowledge.

Whose line is it anyway?

The line between what is the builder’s responsibility and what is a consultant’s responsibility is a difficult one for the law to trace. There are no hard and fast rules, especially as much will depend on the particular builder-consultant contract.

There will be cases where a commercial builder, given its expertise and experience, will be expected to identify and correct errors by another building professional.

However, in this case Judge Woodward ruled that “where (as here) the skill involved is beyond that which can be expected of a reasonably competent builder and there is no actual relevant knowledge”, the liability of a skilled consultant will be possible.

Knowledge of consultants

The lack of knowledge about the combustibility of ACPs, and the failure of the few who had this knowledge to pass it around, proved very costly and almost deadly.

In another important lesson for consultants, the building surveyor tried to argue that because its peers held similar (incorrect) assumptions about ACPs and their compliance with the BCA, it should not be liable. However, Judge Woodward was unimpressed, as these incorrect assumptions formed “organically and apparently without any practitioner seeking any kind of assessment or endorsement from a professional body or regulatory authority”.

Uncritically adopting a practice perceived to be widespread will not save a consultant. He or she must logically consider each issue they come across, and seek professional advice such as that of a fire engineer.

Conclusion

The judge emphasised that this decision was based on the specific facts of the case. If the building contract and the building had been different, or if ACPs had been used on buildings without obvious ignition sources like barbeques and air conditioning units, then the outcome of the case may have been different.

Nevertheless, building owners and consultants, especially those who have been involved in installing combustible cladding, should be on high alert.

They will need to review their building and consulting contracts immediately, not to mention their professional indemnity insurance. This applies not just for current projects, but for previous ones too. The Lacrosse fire happened in 2014 and the companies are paying dearly for it today.

Building owners will also need to go about registering their buildings on the NSW Cladding Registration portal (see link for more).

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email [email protected].

The role of an expert witness in a building dispute

If you are involved in a domestic building dispute, whether as a building professional or homeowner, it will often be beneficial or necessary to retain an expert witness.

The role of an expert witness in a building dispute is to provide objective, qualified and documented evidence relevant to the facts in dispute.

Engaging an expert witness is usually a complex and expensive exercise. Further, the expert’s role as an impartial observer, and not as an advocate for the instructing party, is often misunderstood. Parties to a dispute can become anxious when it appears that the expert they have retained is not “on their side” or that the other party’s expert is an “opponent” in disputed proceedings.

It is therefore helpful to understand the role of expert witnesses, their obligations to a tribunal or court and how they can assist in determining a building dispute.

What is an expert witness?

An expert witness is a qualified professional with both specialised technical knowledge in a particular area or industry, and the necessary skills to provide an opinion, in writing and verbally. This opinion may be used as evidence in negotiations, dispute resolution processes or during tribunal or court proceedings.

When and why is an expert used?

The role of the expert is to assist the parties in negotiating a settlement, or if the matter proceeds to a tribunal or court, guide the decision-maker towards a reasonable determination.

A residential building dispute does not typically concern the interpretation of a contractual term, which, in a court or tribunal, would be a matter for lawyers to argue.

Rather, a residential building dispute typically concerns claims of incomplete and/or defective construction work the nature of which is highly technical and industry specific. The subject matter of the dispute may be a single dwelling or a multi-storey residential complex.

A layperson is not qualified to provide evidence of a technical nature which, in court or tribunal proceedings, could be considered an opinion or hearsay. Similarly, a lawyer is not qualified to assess the costs of rectification of a building.

In such matters evidence should be given by a person with specialised knowledge in the subject matter that is based on his or her training, study or experience. One example of an expert is a quantity surveyor.

Retaining an expert witness

The selection of an expert witness is typically made by the lawyer representing a party to the dispute, who will identify a professional with the necessary expertise required for the particular case and the ability to provide written, and oral evidence, if required.

Written instructions should be provided to the expert which will include an overview of the matter, the issues in dispute, the matters to be addressed, and additional information that will assist in compiling the report, such as building contracts, plans and specifications, and invoices for building materials.

Most unresolved domestic building disputes are heard in a tribunal with specific rules and codes of conduct regarding the use of an expert witness and the required format for expert reports. This is generally to ensure consistency and uniformity. A copy of the relevant expert evidence guidelines and reporting requirements from the tribunal should always be attached to the instructions given to the expert.

It may also be necessary to engage an additional expert with specialist knowledge, such as a structural engineer, to provide a supplementary report for specific issues like a retaining wall claimed to be defective.

A quantity surveyor may be engaged to assess the cost of rectification works for more complex matters. For relatively simple matters, retaining an expert may not be necessary, as obtaining quotes from building professionals and tradespersons may be sufficient.

The expert report

An expert will draw upon his or her construction knowledge to provide a qualified opinion in response to the issues raised in the instructions. A report will typically include:

  • the expert’s formal qualifications, experience and field of expertise in which the evidence is being provided;
  • a summary of the issues upon which the expert is required to report;
  • any facts or assumptions upon which the expert has relied (i.e. the letter of instruction);
  • the identification (and categorisation) of incomplete, non-compliant and/or defective building work;
  • an opinion as to why the building work is incomplete, non-compliant and/or defective, qualified with reference to relevant standards, construction codes and tolerances, and the building contract, plans and specifications;
  • any examinations, investigations or tests used to form the opinion;
  • an assessment of the cause of a defect;
  • recommendations for the rectification of incomplete, non-compliant and/or defective building work including reasons for the recommendation;
  • suggested methods for rectifying the incomplete, non-compliant and/or defective building work including any reasonable alternative remedies;
  • the estimated cost of the recommended rectification work.

The duty of impartiality

Tribunal and court rules, practice notes and directions require that an expert witness is impartial and not an advocate for a party to a proceeding. He or she has an overriding duty to assist a tribunal or court on the matter relevant to the expert’s expertise.

Independence is paramount and any hint of bias towards the instructing party by the expert can be detrimental to that party’s case and may initiate a request by the opposing side for the tribunal to disregard that expert’s evidence.

The expert’s reputation and credibility in such circumstances will also be at stake.

Conclusion

An expert witness may be retained to provide an impartial qualified opinion to assist in determining a matter in dispute.

Choosing an expert with the requisite qualifications, knowledge and experience to provide an objective opinion is essential for many building disputes. When retaining an expert, it is also important to bear in mind that the expert is not an advocate for the instructing party.

If you or someone you know wants more information or needs help or advice, please contact us on +61 2 9248 3450 or email [email protected]