Righting the Wrong in Wrongful Termination

A common reason why an owner may seek to terminate a building contract is that they believe the builder has taken too long to complete the works. They would then claim that the builder has failed to proceed with due diligence under the contract.

For this argument, an owner must be able to show that the builder did not proceed with the works with due diligence within the time stipulated in the contract – which is a breach of the contract and the statutory warranties (as set out in section 18B of the Home Building Act 1989 (HBA)).

This concept of claiming a ‘due diligence breach’ was established in Re Stewardson Stubbs & Collett Pty Ltd v Bankstown Municipal Council [1965] NSWR 1671, which stated that the requirement of due diligence is breached when there is a failing to act with a level of promptness that is expected of a reasonable person undertaking a building project with regard to the contract. However, several cases have since challenged the ease with which owners are able to terminate building contracts by way of alleging a breach of due diligence.

Let’s start with a review of the statutory warranties

Implied into every residential building contract, the HBA states that the works under a building contract will be completed within the time stipulated in the contract or, if there is no time stipulated, within a reasonable time. For example, it must take into account instances that are out of the builder’s control such as third party delays. The HBA also determines that the owners must allow reasonable access to the site for builders who may be seeking to rectify any defects.

Turner Corporation Ltd (Receiver and Manager Appointed) v Austotel Pty Ltd (1994) BCL 378

In this case, Turner appealed the decision in favour of Austotel for the recovery of costs of engaging third parties to rectify defects in Turner’s work without notice and without allowing Turner to rectify the defects. The Court found that the owner did not follow the procedural steps and notice provisions in the contract relating to the defects. Here it is important to acknowledge sections 18BA(3)(a) and (b) of the HBA whereby the owners, through their own conduct, prevented Turner from rectifying the defects and were ultimately unsuccessful as a result.

Hometeam Constructions Pty Ltd v McCauley [2005] NSWCA 303

In this case, it was decided that practical completion of the building work would be in May 2000, and in July of the same year a notice of default was served on the builder for failing to proceed with the building works with due diligence, and by the date for practical completion. In August 2000, the owners terminated the contract, claiming that the builders had failed to remedy the situation. The Court held that there had been no breach of contract, and the builder’s delay and lack of programme for completion, was not enough to amount to a substantial breach of due diligence.

Patel v Redmyre Group Limited [2021] NSWCATAP 132

In this case, the builder worked on the restoration of a residential apartment terrace which was to be completed within 32 weeks. However, the building was not complete by the time specified in the contract and the owners issued a notice of termination with immediate effect. At the time the notice was issued to the builder, the work was 26 weeks behind schedule. The builder sought to rectify the defects, but the owner did not allow access to the site. NCAT held that the builder did not fail to proceed with due diligence and no damages for delay or incomplete works were awarded as the owners failed to mitigate the loss and provide reasonable access to rectify the defects.

THINGS TO CONSIDER

In summary, whether you are a builder or an owner, there are some useful points derived from these cases that may be helpful in understanding if there has been a failure on the part of the builder to proceed with the works with due diligence:

  1. What is the reasonable and relevant time period for a diligent builder to complete the works?
  2. Whether the works are incomplete and, if so, whether there are any circumstances preventing the builder from performance of the works, as well as the pace of performance. This may include any disputes in relation to payment, lack of instructions, a change in scope, request(s) for variations, all of which would cause delay;
  3. Whether there is a lack of activity on the project for a significant period of time that cannot be satisfactorily explained;
  4. Whether the owner mitigated his/her/its loss by allowing reasonable access to the site for the builder to rectify its defects; and
  5. Whether the builder issued extension of time claims and updated programmes if required by the contract.

Terminating a contract based on the failure to proceed with due diligence is a risky one and this is why it must be approached carefully. Otherwise, the owners claiming a breach of due diligence could be found to have repudiated the contract and be liable for damages.

Legal advice should always be sought before terminating a contract.

If you have questions or would like to discuss this article, please contact us.