Tag Archive for: building and construction

Remember your umbrella! Drafting umbrella contracts for a rainy day.

This article focuses on risks for construction contractors and suppliers when agreeing to standing, purchase order or umbrella contracts and provides some tips on how to avoid or mitigate those risks.

“Standing”, “purchase order” or “umbrella” contracts are frequently used where:

  • the client engages, or intends to engage, a contractor or supplier across in multiple projects; or
  • where the quantity of works, goods or services or time when those works, goods or services are required is unclear or subject to change.

Umbrella contracts aim to settle a set of standard terms and conditions with which both parties are comfortable, with the variables such as quantities and time for performance set out in the purchase order later.

Purchase order contains additional adverse terms or terms that conflict with the umbrella contract

A risk in using umbrella contracts is that the client issues a purchase order which includes or appends an additional set of terms and conditions which are not agreeable to the contractor and/or conflict with the umbrella contract.  If the contractor commences performances in accordance with that purchase order or otherwise does not raise objection within a reasonable time:

  • a “battle of the forms” may occur, where which terms and conditions prevail becomes debatable; and/or
  • the client’s purchase order terms may be considered accepted due to the contractor’s performance of the works or services the subject of the purchase order[1].

Some ways that the risk can be avoided or mitigated include:

  1. Prevent inconsistency: Ensure that the umbrella contract contains a term which states that it will apply to the extent of any inconsistency with the purchase order.
  2. Settle form: Ensure that the umbrella contract contains a term which requires any purchase order issued to be in the form appended to the contract as an annexure (and ensuring that the purchase order issued aligns to that form).
  3. Minimise variables: Minimise the amount of variable information that will be subject to the purchase order. The parties should agree as many terms as possible via the umbrella agreement and leaving the purchase order less work to do.
  4. Contractor’s acceptance: Include a term in the umbrella contract that the purchase order will not become operative (i.e. an agreement on its terms reached) unless the contractor accepts the purchase order in writing. Then, do not accept the purchase order in writing unless the variable terms included in it (such as the time for delivery of goods) are achievable.
  5. Limits on liability: Ensure the umbrella agreement contains all necessary limits on liability – e.g. a cap on liquidated damages.

Creation of multiple contracts

It is not uncommon for an umbrella contract to contain a term to the effect that a separate contract is created upon issue (or acceptance) of each purchase order.  This is generally desirable when the umbrella contract is intended to operate as a standing agreed set of terms governing the parties’ relationship across multiple projects.

However, where such a term is included and multiple purchase orders are issued on the one project, such a term can:

  • create general difficulties in administering the contracts and enforcing rights under those contracts; and
  • impact the operation of security of payment legislation.

On the first issue, the parties would need to issue contractual notices with reference to various purchase orders.  For example, in the event of a delay event occurring which impacts multiple purchase orders a notice would need to be issued to the client with reference each separate purchase order, satisfying all relevant criteria under the umbrella agreement for such a notice.  By way of another example, a dispute between the parties may arise due to non-payment of various purchase orders or defects in goods or services supplied under various purchase orders that may need to be individually pursued using the relevant contractual dispute mechanism.

On the second issue, the security of payment legislation in NSW (and other States and Territories) does not permit a payment claim being served (and adjudication application being made) across multiple contracts.

If there is a clause in the umbrella contract stating that each purchase order will give rise to a new contract, the contractor must submit separate payment claims in relation to each purchase order and pursue separate adjudications on each payment claim.

This was highlighted in a case where Holcim pursued an adjudication application against Acciona for work on the Sydney Light Rail project where some 12,500 purchase orders had been issued.  The New South Wales Supreme Court determined that Holcim’s payment claim which encompassed several purchase orders was not a valid payment claim[2] and Holcim lost out on the benefit of an adjudication determination worth nearly $3M.  In this type of case, the issuing of purchase orders which created separate contracts resulted in commercial and administrative unworkability and prejudiced the subcontractor’s ability to pursue a large adjudication against the head contractor.

Whether or not the umbrella contract should contain a clause which provides that each purchase order issued will give rise to a new contract should be considered on a case-by-case basis.

[1] Both of these risks are discussed in our previous article on Samios Plumbing Pty Ltd v John R Keith (QLD) Pty Ltd [2019] QDC 237.

[2] Acciona v Holcim [2020] NSWSC 1330 at [40].

Attention residential builders in NSW – big changes ahead from 1 March 2021 you will be able to use the Building and Construction Industry Security of Payment Act to recover money owed by homeowners

On 1 September 2020, the NSW Government released the Building and Construction Industry Security of Payment Regulation 2020 (2020 Regulation) which radically changes the way residential builders and homeowners resolve disputes in relation to outstanding progress claims after 1 March 2021.

Currently, section 7(5) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) and section 4(1) of the Act provide that the Act does not apply to owner occupier construction contracts, that is, contracts where the homeowners intend to live in the premises.  In these instances, residential builders cannot use the Act to recover outstanding progress claims due from homeowners.

This will all change on 1 March 2021 when the 2020 Regulation commences which will remove owner occupier construction contracts as a prescribed class to which the Act does not apply.

This means come 1 March 2021, residential builders will have a statutory right to payment and be able to serve payment claims on homeowners under the Act and apply for adjudication in relation to any outstanding progress claims.

This is a big game changer for residential builders as it will improve cash flow and mean that residential builders will be able to claim outstanding progress claims from homeowners without having to get involved in expensive and lengthy Tribunal and Court proceedings in order to get paid.

Whilst homeowners will still be entitled to bring a building claim in the Tribunal or Court for defective work and the like, such a claim will not defeat or delay residential builder’s entitlements under the Act.  This means that homeowners will be required to pay any amount awarded pursuant to an Adjudication Determination prior to the determination of any Tribunal or Court proceedings which will (in most cases) reduce in the issues in dispute in any Tribunal or Court proceedings.

What residential builders need to know now

The NSW Government has given residential builders and homeowners a transition period to adjust to these major reforms.  We suggest during this period residential builders should familiarise themselves with the Act and their contracts in relation to:

  • the requirements of valid payment claims including serving supporting statements with all payment claims where builders contract directly with homeowners;
  • the dates from and methods of service of valid payment claims;
  • identification of a valid payment schedules by homeowners;
  • review of your standard contracts to ensure that they comply with the minimum contracting requirements and minimum variation requirements under the Home Building Act 1989 NSW (HBA), as this may effect how an adjudicator assesses amounts payable under the contract so your paperwork has to be in order;
  • review your practices and procedures to ensure that you have the necessary resources to utilise the adjudication process and respond within the strict time frames. The benefit of this is that it will reduce the time and cost (in most cases) of litigation as an Adjudication Determination will usually be received within 21 days of lodging the Adjudication Application; and
  • get legal advice to set yourself up so you can utilise the Act and put yourself in the best position to get paid.

Nominal liquidated damages may not keep general damages away

A Building Contract usually contains a provision for a cap on liquidated damages. In some contracts, particularly Master Builders and HIA contracts, the amount for liquidated damages is usually a default position (unless otherwise stated) at $1 a day for each day of delay from the date the builder was meant to reach completion under the Building Contract until the builder actually completes the works.

The amount set for liquidated damages is meant to represent a genuine pre-estimate of loss that would be suffered by the principal should the works be delayed. If the amount of liquidated damages is excessive, it may be argued that such a clause is a penalty and thus be held to be void.

In the recent case of Cappello v Hammond & Simonds NSW Pty Ltd [2020] NSWSC 1021, the Supreme Court of NSW considered whether a Building Contract which contained a provision for a nominal amount of liquidated damages in the amount of $1 per day excluded the homeowner from also claiming general damages for delay.

The contract was a HIA Costs Plus contract for works related to renovations to a dwelling. The homeowner alleged that the builder was approximately seven months late in completing the works. The Homeowner claimed that it was entitled to general damages, in addition to the claim for the amount of liquidated damages.

The general principle in law is that where parties agree on a rate for liquidated damages, it is taken to exclude claims for general damages.

Justice Ball stated [at paragraph 27]:

“Accepting that principle, the question remains whether by inserting a nominal amount as the amount payable by way of liquidated damages the parties intended, in effect, to exclude the operation of the liquidated damages clause or whether they intended to exclude a right to claim damages for delay altogether. The answer to that question does not depend on the application of any general principle but on the proper construction of the contract in question.” (Emphasis added)

It was also noted that Section 18B(1)(d) of the Home Building Act 1989 (NSW) implies into a residential Building Contract a warranty that the builder will complete the works within the time stipulated in the Building Contract. If the Building Contract seeks to limit a party from claiming damages in the form of nominal liquidated damages it has the effect of restricting that party’s rights in respect of the warranty and would be held to be void under Section 18G of the Home Building Act 1989 (NSW).

Justice Ball held that he preferred the interpretation that if only a nominal amount of liquidated damages is provided for under a Building Contract, it should not be interpreted as preventing a claim for general damages. Accordingly, the parties intend that general damages can be claimed rather than limiting it to the amount of the nominal amount of liquidated damages.

However, Justice Ball ultimately upheld in this case that the Home Owner was only entitled to nominal damages as the majority of the delays were due to the Homeowner’s requested variations to the works and did not appear to have suffered any additional loss.

In light of the above, it is important for liquidated damages to represent a genuine pre-estimate of loss, otherwise:

  1. it will either be held to be a penalty if it is too high and thus void; or
  2. if the amount of liquidated damages is only nominal, then it can be also be held to be either void or may not exclude general damages.

If you or someone you may know is in need of assistance or clarification regarding the above, please email us at info@bradburylegal.com.au or call (02) 9248 3450.

How the new 2020 SOPA Regulation will affect owner occupier construction contracts: the key changes that you need to know

Following our article HERE that summarised the reforms introduced by the Building and Construction Industry Security of Payment Regulation 2020 (NSW) (2020 Regulation), this article explains in detail one of the key reforms.

Reform effecting owner occupier construction contracts

Currently, section 7(5) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) and clause 4(1) of the provide that the Act does not apply to the prescribed class of owner occupier construction contracts.

An owner occupier construction contract is a construction contract for the carrying out of residential building work (as defined in the Home Building Act 1989 (NSW)) on such part of any premises as the party for whom the work is carried out resides or proposes to reside in. Accordingly, for this type of construction contract, builders are not able to apply for adjudication if there is a payment dispute.

This position will change when Schedule 2 of the 2020 Regulation commences on 1 March 2021. Schedule 2 of the 2020 Regulation will omit the current clause 4(1) of the 2020 Regulation and remove owner occupier construction contracts as a prescribed class to which the Act does not apply. The effect of this is will be that the Act will apply to owner occupier construction contracts so that builders will be able to serve payment claims on owner occupiers under the Act and apply for adjudication.

What residential home builders and owner occupiers need to know

While the 2020 Regulation commenced on 1 September 2020 and currently provides that the Act does not apply to owner occupied construction contracts, it seems that the NSW Government has provided residential home builders and owner occupiers with a transition period to adjust to the reform.

The period from now until 1 March 2021 should be utilised to understand how the changes will effect residential home builders and owner occupiers. Importantly, both parties should be aware that:

  • Residential home builders will be able to serve payment claims pursuant to the Act on owner occupiers.
  • Owner occupiers should familiarise themselves with the Act as it will apply to contracts entered into for residential building work at their residence (or proposed residence). Most significantly, owner occupiers should be aware of the requirement to serve a payment schedule within 10 business days after the payment claims is served by the builder if the amount claimed is disputed and will not be paid in full. The consequences of not serving a payment schedule within the timeframe prescribed in the Act are serious and may compromise an owner occupier’s right to participate in an adjudication.
  • The due date for payments will be effected. In accordance with section 11(1C) of the Act, a progress payment becomes due and payable on the date on which the payment becomes due and payable in accordance with the contract or within 10 business days after a payment claim is made (if the contract has no express provision regarding the due date for payment).
  • As the adjudication process is relatively quick and cheap to recover progress payments compared to litigation (in some circumstances), it is likely that adjudication will become a popular method for resolving payment disputes under owner occupier construction contracts.

If you would like to discuss or would like any more information, please contact us at info@bradburylegal.com.au or (02) 9248 3450.

 

 

Spring is here and so is the Building and Construction Industry Security of Payment Regulation 2020

On 1 September 2020, the Building and Construction Industry Security of Payment Regulation 2020 commenced (2020 Regulation) repealing the 2008 Regulation.

The 2020 Regulation will provide the legislative support and administrative detail for the operation of the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) as provided by the amendments which commenced on 21 October 2019. These amendments came about to address poor payment practices and the high incidence of insolvencies in the building and construction industry and also, to facilitate prompt payment, preserve cash flow and resolve disputes quickly and efficiently.

The 2020 Regulation is not retrospective and will not apply to contracts entered into prior to its commencement date.

Key reforms of the 2020 Regulation include:

  • removing the annual reporting requirements for trust accounts to NSW Fair Trading,
  • introducing a requirement for head contractors to keep a ledger for retention money held in relation to each subcontractor and provide the subcontractor with a copy of a ledger at least once every 3 months or longer period of 6 months if agreed in writing, and also to provide trust account records to subcontractors if their money is held in trust,
  • supporting statements are only required for subcontractors or suppliers directly engaged by the head contractor,
  • removing owner occupier construction contracts as a prescribed class of construction contract to which the Act does not apply, and
  • introducing qualifications and eligibility requirements for adjudicators to improve the quality of adjudication determinations under the Act.  The eligibility requirements include either a degree or diploma in a relevant specified field with at least 5 years’ experience, or at least 10 years’ experience in a relevant specified field.  The continuing professional development requirements for adjudicators will commence on 1 September 2021.

Of particular note, the project value threshold (value of the head contractor’s contract with the principal) for retention money trust account requirements will not be reduced from $20 million to $10 million as previously foreshadowed. The existing threshold will remain. Perhaps, given the current climate, it was considered too much of an administrative burden on head contractors who are already dealing with the pressures of delivering projects during Covid. A copy of the 2020 Regulation is  here.

If you would like to discuss or would like any more information, please contact us at info@bradburylegal.com.au or (02) 9248 3450.

If you would like to receive our regular newsletters, please click  here.

When are settlement agreements concerning payment claims void under SOPA?

If a respondent fails to issue a payment schedule in time, but the parties then reach a settlement agreement in relation to the payment claim and construction contract, can the claimant still pursue summary judgment for the full claimed amount due to s.34 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA)?

Facts

In Reward Interiors Pty Ltd v Master Fabrication (NSW AU) Pty Ltd [2020] NSWSC 1251, the claimant served a payment claim and the respondent did not respond within 10 business days as required by the SOPA.  The parties attended a meeting three weeks after the payment claim was issued and agreed to a reduced amount to be paid on the payment claim.[1]  The respondent paid the settlement amount the following day.[2]

The respondent then commenced proceedings against the claimant for damages arising from work performed by the claimant.

The claimant cross-claimed and sought summary judgment on the full payment claim amount. The claimant argued that s.34, which prohibits parties from contracting out of the SOPA, rendered the settlement agreement void.[3]

Decision

The claimant offered no authority for the argument that s.34 of the SOPA renders void settlement agreements which compromise a dispute concerning an amount claimed in a payment claim or the construction contract between the parties generally.[4]  The claimant had agreed not to move for summary judgment on the full claimed amount by accepting the reduced settlement amount.[5]

Stevenson J held that it was at least arguable that the settlement agreement was not rendered void because it acknowledged the operation of the SOPA, yet recorded the parties’ intention that in the particular circumstances their rights would instead be governed by their agreement.[6]  This did not constitute an ‘attempt to deter a person from taking action under’ the SOPA.[7]

Tips for binding settlement agreements on payment claims

The answer to the question posed in the introduction is no.  Assuming the settlement agreement seeks to properly compromise existing entitlements, it will not be voided by s.34 of the SOPA.

The terms should be clearly expressed and specific.  It should state that the claimant has agreed to accept the settlement amount in “full and final satisfaction” of the payment claim and claims made in the payment claim. The terms should provide that once the respondent pays the settlement amount, the claimant “releases” the respondent from any claims or proceedings in respect of the payment claim and claims made in the payment claim.

Where settlement agreement may be rendered void under s 34 is where it seeks to exclude or restrict rights or entitlements arising in the future.  For example, where the parties simply agree (without more) that the claimant will have no entitlement to submit further payment claims.

Of course, the respondent should always serve a proper payment schedule (scheduling nil or a reduced amount and giving reasons) in response to a payment claim, even if confident in securing a settlement, in order to avoid the type of argument raised in Reward Interiors.

[1] At [11].

[2] At [14].

[3] At [15].

[4] At [19].

[5] At [23].

[6] At [24] and [26].

[7] At [25], re s.34(2)(b).