Tag Archive for: building dispute

CONTRACTOR STRIKES SECURITY OF PAYMENT GOLD BY SKIRTING THE MINING EXCEPTION

Mining owners and operators in most Australian States[1] will be aware of the “mining exception” in security of payment legislation.  The mining exception excludes ‘the extraction (whether by underground or surface working) of minerals, including tunnelling or boring, or constructing underground works for that purpose[2] (Mining Exception) from the definition of the term “construction work” and, consequently, the ambit of statutory interim progress payment mechanisms.

However, in a decision handed down on 11 November 2020, the NSW Supreme Court[3] followed the approach of the Queensland courts[4] by construing the Mining Exception narrowly in favour of contractors and subcontractors.  In short, the Mining Exception does not  extend generally to some broad category of mining industry operations.[5]

Facts

Downer EDI Mining Pty Ltd (Downer) was engaged by Cadia Holdings Pty Ltd (Cadia) the operator of the Cadia East underground panel cave mine south-west of Orange, under a “Works Contract” dated 16 November 2018 (Contract), to perform “development phase” works, being (for the most part) underground works to provide access to the proposed undercut and extraction levels for future extraction of minerals in the “production phase”[6]

Downer proceeded to adjudication on a payment claim served on Cadia.  An adjudicator appointed under the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA) determined that Cadia pay Downer $1,017,741.72.[7]

Cadia challenged the determination on two grounds:

  1. the Mining Exception applied so the Contract was not a “construction contract” within the meaning of the SOPA; and
  2. there was no available reference date to support Downer’s payment claim.

Decision

Cadia’s challenge to the adjudication determination was unsuccessful on both grounds.

Stevenson J framed the effect of the Mining Exception as excluding ‘from the definition of “construction work”, the following works:

  • extraction (whether by underground or surface working) of minerals;
  • tunnelling or boring for the purpose of extraction (whether by underground or surface working of minerals; and
  • constructing underground works for the purpose of extraction (whether by underground or surface working) of minerals.[8]

His Honour held that the heart of the question of the application of the Mining Exception to a contract is what a contractor undertakes to do under the contract in question, not what work that contractor actually does[9] (which comes to be answered later).

The works under the Contract did include “tunnelling or boring” as well as “constructing underground works”.  However:

  1. these activities were not for the “purpose of” extraction of minerals; and
  2. the Contract required Downer to undertake work beyond these activities which fell within the meaning of “construction work” or the supply of “related goods and services”.

On considering generally whether activities performed by a contractor are for the “purpose of” extraction of minerals, His Honour:

  1. agreed with Fryberg J in Thiess that the relevant purpose should be decided ‘by reference to what a reasonable person in the position of the parties would conclude as to the object of what purpose of the contract[10];
  2. held that the Mining Exception is to be construed narrowly to benefit the subcontractor[11];
  3. held that a close “proximity” between the act of extraction and the tunnelling and boring or construction of underground works was required (and this was not so in this case, where the extraction phase would not begin until 2022 after subsequent works)[12];
  4. considered that “extraction” does not include work “associated with” or “preparatory to” extraction[13]; and
  5. noted that the SOPA expresses where there is an intention to bring in ancillary activities, which is not the case with the Mining Exception[14].

Further, in this case, His Honour considered that some works under the Contract required of Downer were “construction work” or supply of “related goods and services”, meaning the SOPA applied.  Relevantly, His Honour stated (accepting Downer’s counsel’s submission):

…if there is a contract which contains undertakings to carry out construction work and undertakings to carry out work that it not construction work, the contract remains a construction contract. If a payment claim includes a claim for work that is not construction work, the payment claim is valid, but the adjudicator should not award an amount for work that is not construction work. Thus, the Mining Exception has an important role to play in limiting the amount that the adjudicator should award.[15]

On the reference date point, His Honour determined that there was an available reference date under the Contract for the service of the payment claim.  Most of the points raised were of limited significance for general application.  One point of general interest was that a clause of the Contract required Downer to invoice ‘in respect of the Services performed’ of the proceeding month.[16]  Downer’s works were performed not in the preceding month, but at an earlier time.

His Honour relied on s.13(4) of the SOPA which allows a contractor to serve a payment claim within the period determined under the construction contract or 12 months after construction work to which the claim relates was last carried out.  The payment clause in the Contract attempted to restrict the operation of s.13(4) and was a void provision, by operation of s.34 of the SOPA.

Take Home Tips

Contractors who consider that they are not entitled to have recourse to security of payment legislation simply because they work on a mine site should re-examine closely the terms of their contract.  Can it really be said that the contract works are for the “purpose of” extraction?  Or is there some distance between the works to be performed and the eventual act of extraction?

Perhaps there are portions or stages of works under the contract to which the Mining Exception would apply, but this would not necessarily mean that the entire contract is not a “construction contract” within the meaning of the security of payment legislation.

 

 

[1] Queensland, Victoria, South Australia, Tasmania and the Australian Capital Territory.  However, Western Australia is likely to shortly follow suit once the Building and Construction Industry (Security of Payment) Bill 2020 (WA) passes through Parliament.

[2] Section 5(2) of the Building and Construction Industry (Security of Payment) Act 1999 (NSW).

[3] Cadia Holdings Pty Ltd v Downer EDI Mining Pty Ltd [2020] NSWSC 1588 per Stevenson J.

[4] HM Hire Pty Limited v National Plant and Equipment Pty Ltd [2012] QSC 4 and Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QCA 276 (Thiess)

[5] At [133].

[6] At [92] and [93].

[7] At [3].

[8] At [34].

[9] At [70].

[10] At [96], quoting Fryberg J in Thiess at [76].

[11] At [102]

[12] At [103] and [91].

[13] At [104].

[14] At [105].

[15] At [134].

[16] At [171].

The West Gate Tunnel leads to arbitration

The D&C JV contractors on the West Gate Tunnel (Project), CPB Contractors and John Holland (Subcontractors), have won the first round in their dispute against Transurban (Project Co) over the presence of contaminated “PFAS” soil in the tunnel area and subsequent purported termination of their contract due to force majeure.

In Transurban WGT Co v CPB Contractors Pty Ltd [2020] VSC 476, Victorian Supreme Court (VSC) refused applications designed to prevent the disputes from proceeding through arbitration.

Facts

The Subcontractors purported to terminate their contract with Project Co on 28 January 2020 due to the discovery and persistence of “PFAS” contamination, which it claimed was a “Force Majeure Termination Event” under the contract.[1] Since this time, the Subcontractors and Project Co have been engaged in disputes on the validity of the termination and various related matters.

By notice dated 2 March 2020, the Subcontractors sought to initiate a “downstream” arbitration with Project Co in relation to various claims.[2] Some 3 months later, Project Co initiated its own “upstream” arbitration in relation to various claims which it had passed upstream via its head contract with the State of Victoria.[3]

Project Co claimed the disputes were “Linked Disputes” under the contract with the Subcontractors. Project Co argued that clause 44A.3(a)(ii) operated to suspend the downstream arbitration while the upstream arbitration progressed (suspension clause).[4]

The Subcontractors sought to refer their various disputes with Project Co to arbitration. Project Co made an application for:

  1. a declaration that the suspension clause was enforceable; and

 

  1. an interlocutory injunction to restrain the Subcontractors from taking steps to progress the downstream arbitration until such time as the upstream arbitration was determined.[5]

The Subcontractor argued that the arbitral tribunal should decide whether to grant such relief to Project Co, not the court. The Subcontractor pointed to ss 5, 8, 9 and 17J of the CAAs which provide only limited powers for court intervention.[6]

The Subcontractor made a referral application to the VSC relying on s 5 and / or 8 of the Commercial Arbitration Act 2011 (Vic) (CAA), requesting the court refer Project Co’s query in relation to the operation of the suspension clause to the arbitral tribunal.[7]

Decision

Lyons J:

  1. found that the court had no power to make a declaration of the kind sought by Project Co;

 

  1. refused Project Co’s application for interlocutory injunctions; and

 

  1. granted the Subcontractor’s application to refer to the arbitral tribunal the question of whether the suspension clause was inoperative.[8]

Lyons J considered in detail the relevant law on the nature of arbitration and the limited ambit given to the court under the CAA. Some of His Honour’s key conclusions included that:

  1. the question whether the suspension clause is valid and enforceable was a matter ‘arising in connection with’ the contract between the parties and, therefore, it was a type of dispute the parties had agreed under their contract would be arbitrable;[9]

 

  1. the arbitral tribunal had the power to make orders relating to the validity, enforceability and/or applicability of the suspension clause of the kind sought by Project Co in court;[10]

 

  1. under the CAA the court’s power to grant interlocutory relief to matters which the CAAs apply derives from s 17J[11]. Accordingly, the court’s power to intervene is limited; and

 

  1. Project Co had failed to establish that the circumstances of the case were exceptional or objectively urgent such that court intervention was required.[12]

As a result, the Subcontractor’s claims in relation to the contract will be heard and determined by an arbitrator. The arbitrator will need to determine whether the suspension clause is enforceable and, if so, operates in the circumstances to pause the downstream arbitration.

Take Home Tip

Parties who agree to arbitration as their preferred dispute resolution forum should note that the courts are increasingly minded to allow arbitral tribunals to rule on their own jurisdiction or “competence” under the CAA. A party should closely consider whether their set of circumstances are truly urgent or exceptional to warrant intervention by the court. If not, it would be better to apply its resources in ventilating preliminary issues in the arbitration first, then challenging the arbitrator’s determination on those issues if necessary and as permitted by the CAA.

Importantly, Lyons J considered that he was bound by Hancock v Rhodes[13], being ‘a decision of an intermediate appellate court in circumstances applying sections of a uniform commercial arbitration act in force in each state in Australia.[14] This reinforces the relevance of the current decision of the VSC to parties in all States and Territories in Australia.

[1] At [10(1)].

[2] At [12].

[3] At [12].

[4] At [14].

[5] At [23].

[6] At [115] and [128].

[7] At [20].

[8] At [208].

[9] At [170].

[10] At [174].

[11] At [147] and [191].

[12] At [192] to [203].

[13] Hancock Prospecting Pty Ltd v DFD Rhodes Pty Ltd [2020] WASCA 77.

[14] At [147].

Is the arbitration agreement “not applicable”?

In Gemcan Constructions Pty Ltd v Westbourne Grammar School [2020] VSC 429, Lyons J of the Victorian Supreme Court (VSC) was required to consider whether the terms of the contract contained a valid arbitration agreement within the meaning of s 7 of the Commercial Arbitration Act 2011 (Vic) (CAA). His Honour found that inserting the words “Not Applicable” or “N/A” into corresponding items of Annexure Part A in an otherwise unamended Australian Standard (AS) contract may not evince the necessary intention that relevant clauses do not otherwise apply.

The case not only provides insight into when the court will find that a binding arbitration agreement exists, but also suggests that caution is required at the time of drafting an AS contract.

The case is relevant Australia-wide concerning the application of the CAA because uniform legislation has been enacted in all Australian states and territories.

Facts

On or about 25 July 2016, Gemcan Constructions Pty Ltd (Gemcan) entered into a contract for works to take place at Westbourne Grammar School’s (WGS) Williamstown Campus in Victoria. The contract was a standard form AS 4000-1997 which included the usual:

  • AS 4000 -1997 General Conditions of Contract;
  • particulars at Annexure Part A; and
  • deletions, amendments and additions at Annexure Part B.

A dispute arose between the parties via the exchange of a payment claim and payment certificate issued under their contract. The value of the dispute was circa $1.4 million and included contract works claims, variations, other heads of additional cost, extensions of time, liquidated damages, interest and retention.

Clause 42 of the contract was the dispute resolution clause. Clause 42.2 provided that (inter alia):

If the dispute has not been resolved within 28 days of service of the notice of dispute, that dispute shall be and is hereby referred to arbitration.

Clause 42.3 then went on to provide:

If within a further 14 days the parties have not agreed upon an arbitrator, the arbitrator shall be nominated by the person in Item 32(a). The arbitration shall be conducted in accordance with the rules in Item 32(b).

However, Items 32(a) and 32(b) respectively in Annexure Part A were completed with the words “Not Applicable”.

As the dispute had not been resolved in the time specified in clause 42.2, Gemcan sought to refer the dispute to arbitration and put WGS on notice of its preferred arbitrator.

WGS responded disputing that there was an arbitration agreement in existence because by the parties completing Annexure Part A items with “Not Applicable”, the parties had evinced an intention that its disputes would not be referred to arbitration. If there was no valid arbitration agreement within the meaning of the CAAs, the CAA would not apply and WGS could not be forced to arbitrate.

WGS also disputed Gemcan’s choice of arbitrator, chiefly because he was around twice as expensive as WGS’s selection – a more junior barrister. Gemcan’s view was that its arbitrator was much more experienced in arbitrations generally and had greater legal expertise, as he was senior counsel.

Decision

Lyons J determined:

  • clause 42.2 of the contract constituted a valid agreement to refer the dispute to arbitration, so that the CAA applied; and
  • Gemcan’s arbitrator should be appointed pursuant to s 11 of the CAA.

Whether or not there has been a valid arbitration agreement is a precondition to the application of the CAA. Section 7 of the CAA provides the requirements for a valid arbitration agreement.

Lyons J held that an agreement to arbitrate was evident on the terms of the contract because:

  1. clause 42.2 is ‘clear and unambiguous in its terms’.[1] The last sentence of the standard-form clause evince a clear and objective intention that disputes arising under the clause are to be referred to arbitration if they are not resolved within 28 days of the notice of dispute issuing;
  2. the use of the words “Not Applicable” in Items 32(a) and (b) of Annexure Part A do not evince an intention to negate the referral to arbitration because they only refer back to clause 42.3, not clause 42.2. Clause 42.3 only provides for the procedural aspects of the arbitration, not the agreement to arbitrate itself. In the absence of an agreement regarding procedural aspects (including the arbitrator to be appointed and applicable rules, ss 11(3) and 19(2) of the CAA steps in to provide a mechanism for decisions to be made on those issues). Those procedural mechanisms ‘are not essential characteristics of an enforceable arbitration agreement[2];
  3. the parties could have used Annexure B to make necessary amendments to delete the offending words from clause 42.2, but they did not do so.

Further, Lyons J accepted Gemcan’s proposed arbitrator on the basis that the arbitration was:

  1. likely to be both factually and legally complex;
  2. significant in quantum (and thus the importance to the parties);
  3. likely to require clear and precise written reasons.

The arbitrator proposed by Gemcan was more expensive, however he had more experience in contested and complex arbitration decisions such that the choice was ‘likely to result in the arbitration being conducted in the most efficient way’.[3]

Take Home Tip

If you do not want your standard-form contract to refer you to arbitration, you must do more than insert “Not Applicable” into relevant Items in Annexure Part A. You must ensure that the General Conditions of Contract are correctly amended so that you are not forced into arbitration.

NCC 2019 Amendment 1: Changes starting on 1 July 2020

In response to the recommendations of the Shergold Wier Building Confidence Report, the Australian Building Codes Board (ABCB) and the Building Ministers’ Forum have undertaken an out of cycle amendment to the National Construction Code (NCC). While the NCC was not due for review until 2022, the amendment known as “NCC 2019 Amendment 1” will be adopted by all Australian jurisdictions on 1 July 2020.

The NCC is a performance-based code containing technical standards for the design, construction and performance of buildings as well as for plumbing work and drainage systems. It is published and maintained by the ABCB and adopted by each Australian jurisdiction through its own legislation. For example, in NSW the NCC is given effect by the Environmental Planning and Assessment Act 1979 (NSW), the Plumbing and Drainage Act 2011 (NSW) and subordinate legislation.

The aim of the NCC is to create a uniform set of technical standards that apply to all Australian jurisdictions. However, as identified in the Shergold Wier Building Confidence Report, there have been a number of systematic issues with the implementation and enforcement of the NCC which has prompted NCC 2019 Amendment 1.

What will change?

Following a period of key stakeholder consultation last year, NCC 2019 Amendment 1 will introduce the following changes:

  • a new provision regarding egress from early childhood centres (NCC Volume One);
  • clarification of the concession that permits the use of timber framing for low-rise Class 2 and 3 buildings (NCC Volume One);
  • clarification that anti-ponding board requirements only apply to roofs where sarking is installed (NCC Volume Two);
  • an update to the Governing Requirements for all Volumes to require labelling of aluminium composite panels in accordance with SA Technical Specification 5344; and
  • correction of minor errors, including the correction of typographical errors and errors in diagrams.

In addition to the above, the ABCB announced last month that NCC 2019 Amendment 1 will also include a provision mandating the process for developing Performance Solutions. This process is based on the ABCB’s existing Development of Performance Solution Guideline and requires that the process for documenting Performance Solutions be commensurate with the complexity and risk of the design.

Unlike the other amendments, this amendment will not commence until 1 July 2021. However, as the process is included in NCC 2019 Amendment 1 there is plenty of time for industry participants to prepare necessary documentation to encompass the process for Performance Solutions prior to the amendment taking effect next year.

Other changes expected

It was also proposed that NCC 2019 Amendment 1 would include the new defined term of “building complexity”. The draft definition proposes a risk-based system from levels 0 to 5 for classifying complex buildings, which assists to identify buildings where additional regulatory oversight is needed during the design, construction and certification processes.

 

The ABCB announced last month that this new definition would not be included in NCC 2019 Amendment 1, however it has been published on their website with a six month consultation period for comments and feedback.

A copy of the preview of NCC 2019 Amendment 1 is available on the ABCB website via the NCC Suite.

If you or someone you may know is in need of advice regarding NCC 2019 Amendment 1 or the NCC generally, please contact our office by phoning (02) 9248 3450 or by email at [email protected].