Tag Archive for: construction disputes

WESTERN AUSTRALIA LEGISLATIVE REFORMS FOR SECURITY OF PAYMENT- THE BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2021 (WA)

OVERVIEW

The Building and Construction Industry (Security of Payment) Act 2021 (WA) (the “new Act”) will introduce new security of payment laws that aim to provide a higher level of protection for contractors in recovering payments.

The first stage of reforms will take effect on 1 August 2022 and the following stages will be effective from 1 February 2023 (Stage 2) and 1 February 2024 (Stage 3). It is important to note that all construction contracts entered into prior to 1 August 2022 will continue to be subject to the Construction Contracts Act 2004 which, as of the date of enforcement, will be referred to as the Construction Contracts (Former Provisions) Act 2004.

CHANGES TO BE IMPLEMENTED

The new Act introduces additional rights to payment under construction contracts and further avenues to recover payments owed to contractors.

The changes to be implemented include but are not limited to:

New Security of Payment Laws

  • Payment timeframes where a payment claim is made will be shortened to 20 business days for the head contractor on a project, 25 business days for subcontractors, and 10 business days for certain types of home building works;
  • If no payment schedule is provided, the respondent is required to pay the amount claimed and will be unable to respond to any application for adjudication;
  • A rapid adjudication process will be implemented with the time period for bringing an adjudication application being reduced from 90 to 20 business days;
  • There will be a prohibition of certain contract terms including “pay when paid” and unfair time bars; and
  • There will be a right to suspend work for reasons of non-payment of progress claims.

Retention Trust Scheme

A retention trust scheme will now apply to construction contracts valued over $1 million and the minimum contract value for the scheme to be applicable will be lowered to contracts over $20,000 (by regulations).

To protect retention money in the event of insolvency, the money held or withheld under a construction contract will be held in trust for the benefit of the party who provided the money.

Expanding the Powers of Building Industry Regulators

Building industry regulators will now have the authority to exclude persons with a history of financial failure from the registered building contractor market. This is to prevent persons from contracting with incompetent or predatory businesses.

Further, persons who exercise intimidation or threatening behaviour to prevent another from exercising their rights under the new Act may be prosecuted.

 

TO CONSIDER

With the introduction of legislative reforms with regards to security of payment in Western Australia, it is essential for contractors to become familiar with the additional rights that arise under the new Act, and for principals to be aware of the importance of providing a valid payment schedule when served a payment claim and managing their finances accordingly.

If you require further information, please see the Action Plan for Reform dated September 2021 and issued by the Department of Mines, Industry Regulation and Safety, or contact our office to speak to one of our lawyers to discuss how the new Act will apply to your construction contract.

 

Valmont Estopped In Its Tracks by Armani

The issue of estoppel in the context of a rejected variation claim was recently considered by the NSW Court of Appeal in Valmont Interiors Pty Ltd v Giorgio Armani Australia Pty Ltd (No 2) [2021] NSWCA 93.

In this case, Valmont Interiors Pty Ltd (Valmont) was led to assume that it would be paid for additional joinery works that were directed by Giorgio Armani Australia Pty Ltd (Armani) as a purported variation.  However, as the procedure for claiming and approving variations under the contract was not adhered to, Armani sought to rely on the time bar in the variation provision to reject the claim.

Facts

In early 2016, Valmont entered into a contract with Armani to provide fit-out works for the new Emporio Armani store at Sydney Airport. The scope of works originally excluded certain joinery items, which were to be sourced by Armani from a third party supplier. However, shortly after the works commenced, the third party supplier was not able to meet the tight schedule for delivery and Armani directed Valmont to supply the joinery items.

Valmont supplied the joinery items but Armani refused to pay for them on the basis that Valmont did not follow the procedure set out in clause 15 of the contract for claiming a variation and waived its claim.  Relevantly, this clause provided that if Valmont considered that a direction of Armani constituted a variation it was required to give notice of the purported variation within five business days.  This clause also provided that failure to provide notice within the specified time period resulted in Valmont releasing and waiving any entitlement to a claim.

Valmont’s position was that Armani should be estopped from relying on the time bar in clause 15 to reject the claim because Armani did also not follow the procedure in clause 15 for instructing the supply of the additional joinery items (as well as for previous other variations).  As a result of this, Valmont argued that Armani led it to assume that strict compliance with the procedure in clause 15 was not required in order to claim payment for the additional joinery work.

The First Decision

The primary judge held that, although Valmont did not strictly comply with the procedure set out in clause 15 of the contract for claiming a variation, Armani was estopped from relying on the time bar in that clause and that the costs of certain variation were recoverable by Valmont.

However, the primary judge also found that at a certain point in time (being 11 April 2016), email correspondence between the parties corrected Valmont’s assumption that it could claim payment for variations without complying with the procedure set out in clause 15 of the contract and that Armani would rely on strict compliance with that procedure for future variations.  Accordingly, it was held that the estoppel ceased on that date and the costs of purposed variations after that date (including the additional joinery works) were not recoverable.

The Appeal

On appeal the Court disagreed with the primary judge and found that the estoppel continued to operate after the 11 April 2016 email because:

  1. the email did not displace Valmont’s assumption that was induced by Armani that it would be paid for supplying the additional joinery works. This was partly because Armani’s email was not sufficiently clear to correct Valmont’s assumption (ie. that strict compliance with clause 15 of the contract was not required in order to be paid for additional joinery works);
  2. the email conveyed that the supply of the joinery was not a variation but additional works outside of the contract;
  3. Valmont was entitled to expect to be paid for the additional joinery works that were directed by Armani. The fact that it continued to incur liabilities after receiving the email from Armani demonstrated that the email did not correct Valmont’s understanding of the situation.  Further, Valmont relied on that understanding to its detriment, and as it was no longer possible for Valmont to comply with clause 15 of the contract it could not overcome the detriment already suffered; and
  4. in the circumstances, it was unconscionable for Armani to refuse to pay Valmont for the additional joinery works.

Take home tips

We understand that in administering contracts parties do not always strictly comply with the procedures and timing set out in the contract for claims, especially if the parties consider they have a good relationship or believe that strict compliance is too formal.  This case highlights the potential serious consequences of taking that approach.

Parties to a contract should be aware of the risks of acting inconsistently with their rights under the contract (ie. in Armani’s case, not requiring compliance with the terms of the contract for claiming variations and also not formally directing variations), as this could lead to those rights being lost and there not being a basis to reject claims.

If a principal or head contractor (or other party in a similar position) is concerned that a particular state of affairs exists between them and the downstream party that is inconsistent with the contract, it is crucial that the principal or head contractor:

  1. corrects that understanding by stating in clear and precise terms that the current understanding must be departed from and that strict compliance with the contract is required;
  2. provides sufficient notice of this so that the downstream party has time to comply with the procedure in the contract for claims and can attempt to overcome any detriment; and
  3. then strictly requires and enforces the procedure in the contract for claims so as to avoid any doubt that another state of affairs exists between the parties.

 

CONTRACTOR STRIKES SECURITY OF PAYMENT GOLD BY SKIRTING THE MINING EXCEPTION

Mining owners and operators in most Australian States[1] will be aware of the “mining exception” in security of payment legislation.  The mining exception excludes ‘the extraction (whether by underground or surface working) of minerals, including tunnelling or boring, or constructing underground works for that purpose[2] (Mining Exception) from the definition of the term “construction work” and, consequently, the ambit of statutory interim progress payment mechanisms.

However, in a decision handed down on 11 November 2020, the NSW Supreme Court[3] followed the approach of the Queensland courts[4] by construing the Mining Exception narrowly in favour of contractors and subcontractors.  In short, the Mining Exception does not  extend generally to some broad category of mining industry operations.[5]

Facts

Downer EDI Mining Pty Ltd (Downer) was engaged by Cadia Holdings Pty Ltd (Cadia) the operator of the Cadia East underground panel cave mine south-west of Orange, under a “Works Contract” dated 16 November 2018 (Contract), to perform “development phase” works, being (for the most part) underground works to provide access to the proposed undercut and extraction levels for future extraction of minerals in the “production phase”[6]

Downer proceeded to adjudication on a payment claim served on Cadia.  An adjudicator appointed under the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA) determined that Cadia pay Downer $1,017,741.72.[7]

Cadia challenged the determination on two grounds:

  1. the Mining Exception applied so the Contract was not a “construction contract” within the meaning of the SOPA; and
  2. there was no available reference date to support Downer’s payment claim.

Decision

Cadia’s challenge to the adjudication determination was unsuccessful on both grounds.

Stevenson J framed the effect of the Mining Exception as excluding ‘from the definition of “construction work”, the following works:

  • extraction (whether by underground or surface working) of minerals;
  • tunnelling or boring for the purpose of extraction (whether by underground or surface working of minerals; and
  • constructing underground works for the purpose of extraction (whether by underground or surface working) of minerals.[8]

His Honour held that the heart of the question of the application of the Mining Exception to a contract is what a contractor undertakes to do under the contract in question, not what work that contractor actually does[9] (which comes to be answered later).

The works under the Contract did include “tunnelling or boring” as well as “constructing underground works”.  However:

  1. these activities were not for the “purpose of” extraction of minerals; and
  2. the Contract required Downer to undertake work beyond these activities which fell within the meaning of “construction work” or the supply of “related goods and services”.

On considering generally whether activities performed by a contractor are for the “purpose of” extraction of minerals, His Honour:

  1. agreed with Fryberg J in Thiess that the relevant purpose should be decided ‘by reference to what a reasonable person in the position of the parties would conclude as to the object of what purpose of the contract[10];
  2. held that the Mining Exception is to be construed narrowly to benefit the subcontractor[11];
  3. held that a close “proximity” between the act of extraction and the tunnelling and boring or construction of underground works was required (and this was not so in this case, where the extraction phase would not begin until 2022 after subsequent works)[12];
  4. considered that “extraction” does not include work “associated with” or “preparatory to” extraction[13]; and
  5. noted that the SOPA expresses where there is an intention to bring in ancillary activities, which is not the case with the Mining Exception[14].

Further, in this case, His Honour considered that some works under the Contract required of Downer were “construction work” or supply of “related goods and services”, meaning the SOPA applied.  Relevantly, His Honour stated (accepting Downer’s counsel’s submission):

…if there is a contract which contains undertakings to carry out construction work and undertakings to carry out work that it not construction work, the contract remains a construction contract. If a payment claim includes a claim for work that is not construction work, the payment claim is valid, but the adjudicator should not award an amount for work that is not construction work. Thus, the Mining Exception has an important role to play in limiting the amount that the adjudicator should award.[15]

On the reference date point, His Honour determined that there was an available reference date under the Contract for the service of the payment claim.  Most of the points raised were of limited significance for general application.  One point of general interest was that a clause of the Contract required Downer to invoice ‘in respect of the Services performed’ of the proceeding month.[16]  Downer’s works were performed not in the preceding month, but at an earlier time.

His Honour relied on s.13(4) of the SOPA which allows a contractor to serve a payment claim within the period determined under the construction contract or 12 months after construction work to which the claim relates was last carried out.  The payment clause in the Contract attempted to restrict the operation of s.13(4) and was a void provision, by operation of s.34 of the SOPA.

Take Home Tips

Contractors who consider that they are not entitled to have recourse to security of payment legislation simply because they work on a mine site should re-examine closely the terms of their contract.  Can it really be said that the contract works are for the “purpose of” extraction?  Or is there some distance between the works to be performed and the eventual act of extraction?

Perhaps there are portions or stages of works under the contract to which the Mining Exception would apply, but this would not necessarily mean that the entire contract is not a “construction contract” within the meaning of the security of payment legislation.

 

 

[1] Queensland, Victoria, South Australia, Tasmania and the Australian Capital Territory.  However, Western Australia is likely to shortly follow suit once the Building and Construction Industry (Security of Payment) Bill 2020 (WA) passes through Parliament.

[2] Section 5(2) of the Building and Construction Industry (Security of Payment) Act 1999 (NSW).

[3] Cadia Holdings Pty Ltd v Downer EDI Mining Pty Ltd [2020] NSWSC 1588 per Stevenson J.

[4] HM Hire Pty Limited v National Plant and Equipment Pty Ltd [2012] QSC 4 and Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QCA 276 (Thiess)

[5] At [133].

[6] At [92] and [93].

[7] At [3].

[8] At [34].

[9] At [70].

[10] At [96], quoting Fryberg J in Thiess at [76].

[11] At [102]

[12] At [103] and [91].

[13] At [104].

[14] At [105].

[15] At [134].

[16] At [171].

Spring is here and so is the Building and Construction Industry Security of Payment Regulation 2020

On 1 September 2020, the Building and Construction Industry Security of Payment Regulation 2020 commenced (2020 Regulation) repealing the 2008 Regulation.

The 2020 Regulation will provide the legislative support and administrative detail for the operation of the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) as provided by the amendments which commenced on 21 October 2019. These amendments came about to address poor payment practices and the high incidence of insolvencies in the building and construction industry and also, to facilitate prompt payment, preserve cash flow and resolve disputes quickly and efficiently.

The 2020 Regulation is not retrospective and will not apply to contracts entered into prior to its commencement date.

Key reforms of the 2020 Regulation include:

  • removing the annual reporting requirements for trust accounts to NSW Fair Trading,
  • introducing a requirement for head contractors to keep a ledger for retention money held in relation to each subcontractor and provide the subcontractor with a copy of a ledger at least once every 3 months or longer period of 6 months if agreed in writing, and also to provide trust account records to subcontractors if their money is held in trust,
  • supporting statements are only required for subcontractors or suppliers directly engaged by the head contractor,
  • removing owner occupier construction contracts as a prescribed class of construction contract to which the Act does not apply, and
  • introducing qualifications and eligibility requirements for adjudicators to improve the quality of adjudication determinations under the Act.  The eligibility requirements include either a degree or diploma in a relevant specified field with at least 5 years’ experience, or at least 10 years’ experience in a relevant specified field.  The continuing professional development requirements for adjudicators will commence on 1 September 2021.

Of particular note, the project value threshold (value of the head contractor’s contract with the principal) for retention money trust account requirements will not be reduced from $20 million to $10 million as previously foreshadowed. The existing threshold will remain. Perhaps, given the current climate, it was considered too much of an administrative burden on head contractors who are already dealing with the pressures of delivering projects during Covid. A copy of the 2020 Regulation is  here.

If you would like to discuss or would like any more information, please contact us at info@bradburylegal.com.au or (02) 9248 3450.

If you would like to receive our regular newsletters, please click  here.

Contractors – don’t use Dropbox if you want to get paid!

In Wärtsilä Australia Pty Ltd (ACN 003 736 892) v Primero Group Ltd (ACN 139 964 045) & Ors [2020] SASC 162, a contractor has failed to recoup $15M because it tried to submit completion reports via Dropbox link.  This is adds to the line of authorities which caution reliance on cloud-based technologies for issuing documents, whether under contract or statute.

Facts

Primero Group Ltd (Primero) contracted with Wärtsilä Australia Pty Ltd (Wärtsilä) to perform civil, mechanical and electrical works and supply tanks for the construction of the Barker Inlet power station on Torrens Island in South Australia.

The contract provided the following requirements for ‘SW Completion’:

(2) the tests, inspections and communications required by this subcontract (including Schedule 3) to have been carried out before SW Completion have been carried out, passed and the results of the tests, inspections and commissioning provided to [Wärtsilä]

(8) the completed quality assurance documentation … is available for inspection by [Wärtsilä] at the Facility Land’ (emphasis added)

Primero emailed Wärtsilä on 28 February 2020 a Dropbox link to the documents.  Yet Wärtsilä was unable to access the documents via the link until 2 March 2020.

On 2 March 2020, Primero served a payment claim under s 13 of the Building and Construction Industry Security of Payment Act 2009 (SA) in the amount of $85,751,118 (excluding GST).  On 10 March 2020, Wärtsilä responded with a payment schedule which scheduled “nil” but also stated that the payment claim was invalid as it was not supported by a reference date.

Primero proceeded to adjudication and the adjudicator determined Primero’s payment claim was valid, awarding $15,269,674.30 (excluding GST).  Key to the adjudicator’s determination was that the payment claim was supported by a reference date of 28 February 2020.  Wärtsilä made an application to the Supreme Court for an order quashing the adjudication determination.

The parties agreed that if SW Completion under the contract had not occurred on 28 February 2020 the adjudicator’s determination was invalid.[1]

Primero argued that it had provided the documents and made them available for inspection by sending the email.

Primero also contended that the Electronic Communications Act 2000 (SA) (ECA) permitted the contractual obligation for the provision of the documents to be satisfied by electronic communication.  Under s 8 of the ECA, the time of receipt of an electronic communication was when it is ‘capable of being retrieved by the addressee’.

Decision

Sending a Dropbox link to the documents was not sufficient for SW Completion.  On 28 February 2020, Primero had emailed the link to Wärtsilä, but Wärtsilä was unable to completely download the documents.[2]

Accordingly, the adjudication determination was quashed because it was not made with reference to a valid payment claim.[3]  The $15M award to Primero was nullified.

Stanley J held[4]:

  1. in relation to SW Completion item (2), ‘the provision of the hyperlink merely provided a means by which Wärtsilä was permitted to download the documents stored in the cloud. Until it did so, those documents had not been provided.

 

  1. in relation to SW Completion item (8), ‘the hyperlink did not amount to making the documents available for inspection… because until all the documents were downloaded, they were not capable of being inspected at the facility land.’

His Honour stated:

a common sense and businesslike construction of the contractual requirements that the documents be provided and are available for inspection necessarily requires that the documents were capable of being downloaded on 28 February 2020. I find they were not.[5]

Stanley J applied a Queensland case Conveyor & General Engineering v Basetec Services & Anor [2015] 1 Qd R 265 (Conveyor) and a Federal Court case Clarke v Australian Computer Society Inc [2019] FCA 2175 (Clarke), which went to the point that a document could not itself be considered to be “left at” or “sent” to an intended recipient if an email containing a link to the document was sent to that recipient.[6]  To summarise, it is only the email itself which is sent or transmitted, not the document housed on the cloud server.

The ECA did not apply to the communication to solve the problem for Primero because[7]:

Both s 8 and s 10 prescribe circumstances that condition the operation of those provisions. Those circumstances include: first, that at the time the information is given by means of electronic communication, it was reasonable to expect that the information would be readily accessible so as to be useable for subsequent reference; and second, that the person to whom the information is required to be given consents to the information being given by means of an electronic communication.

His Honour held that Conveyor and Clarke stood as authority for the proposition that the provision of the documents by hyperlink did not constitute an “electronic communication” for the purposes for the ECA.

This point is highly relevant to because the relevant legislation governing electronic transmissions and communications are modelled off uniform Commonwealth legislation (Electronic Transactions Act 1999 (Cth)) and have largely consistent provisions.

Take Home Tips

It is important to consider closely whether the terms of your contract allow you to submit completion documents (or other documents) via a Dropbox link.  If the contract uses words like “provide”, “send”, “make available”, etc, it is unlikely that merely providing a link to those documents will satisfy the obligation unless and until the documents are actually downloaded or accessed in full by the intended recipient.  This can be difficult to prove.

It is unlikely that you will be able to fall back on the relevant electronic communications or transactions legislation in your jurisdiction because the provision of the link will not be considered an “electronic communication” of the document itself.  Strict compliance with the contract and statute (particularly in the realm of security of payment) is always required.

[1] At [12].

[2] At [93].

[3] At [128].

[4] At [94].

[5] At [105].

[6] At [98] to [101].

[7] At [117].