Tag Archive for: reference date

Security of payment: no work, no pay

Participants in the commercial building industry generally rely on security of payment legislation to resolve payment disputes. As a preliminary means of recovering money under a construction contract, those in the industry are usually keen to hear of developments regarding a court’s interpretation of the legislative provisions.

Shape Australia Pty Ltd v The Nuance Group (Australia) Pty Ltd [2018] VSC 808 (‘Shape’ and ‘Nuance Group’) recently considered two issues under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the ‘Act’), namely:

  • whether a reference date can be ‘refreshed’ for a payment claim when there has been no further work carried out since the previous reference date; and
  • whether an amount in a payment claim which attempts to recoup liquidated damages (previously offset in a payment schedule) constitutes an ‘excluded amount’ under the Act.

Background

In July 2016, Shape and Nuance Group entered a contract for the demolition and associated works at Melbourne International Airport.

On 2 March 2018, Shape issued payment claim #13 for $3,533,233.84. Nuance Group responded with a payment schedule stating the amount payable as nil. Shape applied for adjudication for a reduced sum of $2,243,105.55.

On 13 April 2018, a First Adjudication Determination for the sum of $1,400,007.12 issued, which after review instigated by Nuance Group, was reduced to $1,216,715.72.

Nuance Group challenged the validity of the original and reviewed determinations and, on 2 June 2018, in Nuance Group (Australia) Pty Limited v Shape Australia Pty Limited [2018] VSC 362 the Court quashed the determination on the basis that the adjudicator had “failed to perform his basic and essential function” under the Act.

Subsequently:

  • On 10 July 2018, Shape issued payment claim #14 for $1,285,579.62 which included “uncontested individual line items claimed in payment claim #13”. Nuance Group responded with a payment schedule stating the amount payable as nil.
  • Shape applied for adjudication, and on 23 August 2018, a Second Adjudication Determination issued which essentially declared the claim invalid for want of a valid reference date and that (in any event) the amount payable was nil on the basis that the claim was for an excluded amount.
  • Shape applied for orders remitting the first or second adjudication determination for review.

Decision

Was the payment claim invalid for want of a reference date?

Section 9(1) of the Act provides that there must be a valid reference date to avail rights for a person to a progress payment. A payment claim must be supported by a valid reference date, which is a precondition to an adjudicator making a determination under the Act.

Clause 42.1 of the construction contract entitled Shape to make payment claims on the 28th day of each month, and that such claims should include “the value of work carried out by the contractor in the performance of the contract to that time …”. On that basis, the Court considered that the requirement for work to be carried out “to that time” established a threshold for making a claim.

Payment claim 14, which had a reference date of 28 June 2018, was identical to payment claim 13, which carried a reference date of 28 February 2018. No further work had been carried out since issuing payment claim 13 and accordingly, 28 February was the last available reference date under the contract.

It followed that payment claim 14 was invalid for “want of a reference date”. The claim was either made in respect of the (same) 28 February reference date and therefore in breach of the Act, or a claim served out of time, namely, outside of the three-month period prescribed by the Act.

Shape’s application was dismissed, the Court agreeing with the adjudicator’s determination and finding nothing further to conclude otherwise.

Are liquidated damages an excluded amount?

The Act sets out certain classes of amounts that are “excluded” and must not be taken into account when calculating an amount of a progress payment. Essentially, excluded amounts include certain variations of the construction contract, amounts claimed for compensation due to the “happening of an event” (latent conditions, time-related costs and changes in regulations), amounts claimed for damages in relation, or incidental to, a breach under the construction contract or other claims arising at law.

The concept of an excluded amount in the Victorian Act underpins a key objective, namely, to facilitate cashflow within the industry by dealing with payment disputes promptly, whilst maintaining the parties’ legal rights to argue more complex issues later.

The Second Adjudication Determination declared the amount payable in the claim as nil on the basis that “…the entirety of the purported claim was for an excluded amount, being an attempt to recoup the first defendant’s asserted entitlement to liquidated damages”.

The Court confirmed this decision, reiterating the adjudicator’s findings that:

  • when the individual items listed in payment claim 14 were “adjusted and reconciled” the total equated “to the amount of Nuance Group’s asserted entitlement to liquidated damages”; and
  • the amount claimed could be “explained on no other basis, given no new work had been performed and the other claims in payment claim 14 [had] been satisfied”.

Takeaways

Seabay Properties Pty Ltd v Galvin Construction Pty Ltd [2011] VSC 183 determined that a set-off claimed in a payment schedule (by way of a deduction in response to a payment claim) constitutes liquidated damages and is therefore, an excluded amount for the purposes of the Act.

The present case however confirmed that an attempt to recoup liquidated damages through a payment claim will also constitute an excluded amount.

Industry participants should take note that:

  • Liquidated damages claimed as an offset in a payment schedule as well as amounts claimed in a payment claim to recoup liquidated damages are excluded amounts for the purposes of the Victorian security of payment legislation.
  • Claimants wishing to dispute liquidated damages should do so at the time they are levied. Where offsets have previously been raised in a payment schedule and the corresponding payment claim settled, a challenge to these levies in a subsequent payment claim will likely be considered an excluded amount.
  • If the right to make a payment claim under a construction contract is subject to the carrying out of work ‘up to the time’ for making the claim, there will be no available reference date unless work has been carried out since the last reference date.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email [email protected].

Does a payment claim survive the termination of a contract for convenience?

Security of payment legislation continues to receive significant attention across Australia’s building and construction landscape, with many cases being deconstructed to shed light on a court’s interpretation of various provisions.

Impero Pacific Group Pty Ltd v Bonheur Holdings Pty Ltd [2019] NSWSC 286 recently established that, despite a construction contract being terminated for convenience, a contractor may still claim for work carried out between the last accrued reference date and the termination date. Much will depend on the wording of the contract.

The decision diverges from previous case law which holds that a contract terminated for convenience does not provide ongoing reference dates, and consequently no entitlement for a contractor to claim for work carried out between the last reference date and termination.

Background

The contractor, Impero Pacific Group Pty Ltd (Impero) entered into a contract with Bonheur Holdings Pty Ltd (Bonheur), as principal, for construction of a residential strata complex, with a completion date of 1 March 2019.

The reference date, for the purposes of making payment claims was the 25th day of the month.

Crucially, the contract contained a termination for convenience clause (clause 39A), allowing the principal at its discretion to terminate the contract and complete any part of the works either itself or through another party. If invoked, the contractor would be entitled to payment for certain works carried out to the date of termination that would otherwise have been payable if the contract had not been terminated.

The contract was terminated for convenience by Bonheur on 29 or 30 October 2018.

Impero served a payment claim on 27 November 2018 for approximately $1.4 million relating to work undertaken between the last reference date being 25 October 2018 and the termination date, namely 29 or 30 October 2018.

Bonheur failed to respond to the claim as required under the Act and Impero sought judgement from the Supreme Court.

Bonheur argued that the payment claim was invalid as it was not supported by an available reference date pursuant to clause 8 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the ‘Act’).  It contended that if the contract was terminated for convenience, “the Act cannot be used to obtain a progress payment for work done between the last contractual progress payment date and the date of termination.”

It was also submitted that, if Impero did have a right to a progress payment, it was “limited to part only” on the basis that it had claimed for items not within the scope of the Act and therefore no judgement could be obtained.

Impero argued that on construction of clause 39A, termination resulted in the creation of a new reference date and a consequential entitlement to claim and receive payment.

Decision

Justice Parker was not persuaded by the principal’s submissions and ordered the judgement sought by Impero.

The Act provides that on and from each reference date under a construction contract a person is entitled to a progress payment for work carried out under the contract.

Justice Parker acknowledged that under the current Act “there is no entitlement to a progress payment, and there can be no valid progress claim, unless there is an available reference date”. A reference date is defined as:

“(a)    a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out…under the contract, or

(b)     if the contract makes no express provision with respect to the matter – the last day of the named month in which the construction work was first carried out…and the last day of each subsequent named month.

The last reference date prior to termination (on 29 or 30 October) was 25 October, which would have been available to claim for work carried out up to that date, but not beyond. Had the contract not been terminated, the next available reference date would have been 25 November.

Justice Parker considered the present matter in the context of previous cases and clause 39A of the construction contract. Clause 39A provided an entitlement for Impero to claim for work carried out under the contract up to the date of termination, and crucially this clause expressly stated that it would survive termination.

In the circumstances it was determined that “termination of the contract gave rise to a fresh reference date for the purposes of the Act and the entitlement for Impero to claim up to termination.

As to the contention that Impero’s right to a progress payment, if awarded, should be limited to part only, Justice Parker confirmed that “the Act does not permit the Court to make its own assessment of the extent to which the claimed amount represents payment for construction work or the supply of related goods or services. In that sense, it is an all-or-nothing provision.” The opportunity for a principal to argue that items fall beyond the scope of the Act arises by serving a payment schedule in response to a contractor’s payment claim. In the present case, the principal failed to do this.

Key takeaways

  • The exercise of a right to terminate a construction contract for convenience will not prevent a contractor from claiming for work carried out up to the termination date;
  • Progress claims should specify the works carried out between the last accrued reference date and the date of termination and relate only to works defined within the scope of the Act; and
  • Principals who terminate a contract for convenience should anticipate that a contractor may make a claim up to the date of termination. Items considered to be claims beyond the scope of the Act should be identified in the payment schedule.

Readers should be aware that Justice Parker makes it clear that termination for convenience is not the same as termination for breach nor is it similar to accepting the repudiation of the other party. The situation may be different in these cases. The High Court of Australia has previously ruled that in these cases, unless the contract expressly provides so, reference dates do not accrue after termination or accepted repudiation.

Where to next?

Determinations such as this are frequently analysed, particularly as participants in the building and construction industry await reforms yet to commence under the Building and Construction Industry Security of Payment Amendment Act 2018 (NSW). For more details on these amendments, click here.

Upon commencement of the current reforms proposed, the reference date system will be abolished, and a contractor will be able to make a progress claim for work carried out up to the date of a terminated contract, whether the contract is terminated for convenience or otherwise.

The policy behind these amendments is to discourage principals from strategically terminating a contract primarily to avoid a final payment claim being made under the Act.

If you or someone you know wants more information or needs help or advice, please contact us on +61 2 9248 3450 or email [email protected].

The Fantastic Fourth: another NSW Security of Payment amendment

On 21 November 2018, the NSW Houses of Parliament passed the Building and Construction Industry Security of Payment Amendment Act 2018 (Amendment Act). This will amend some provisions of the Building and Construction Industry Security of Payment Act 1999 (Security of Payment Act).

Some of these changes are reversions to old systems, while others introduce completely new regimes. Readers will be forgiven for being irritated at yet another shock to the system, but it is vital to become familiar with all of these so that when they come into effect, businesses are ready for them. Directors and managers should take particular note as they will soon be open to criminal proceedings.

We wrote a pocket summary of these changes in December (see here).

Here we expand on the details, and we can now give some indication of when these changes will be activated.

Before going into the detail, readers should take note that as of 5 March 2019, none of these changes have come into effect.

When the changes will come in

This is the most important detail and so far, we don’t know. We will only know for sure after the fact, when the government makes the official announcement in the NSW Government Gazette.

However, a paper released by Fair Trading NSW in December 2018 has given some hints about when to expect these changes. It looks like there will be three main phases of changes throughout 2019 for principals and contractors to weather:

  • Phase 1 changes were proposed to come in during February 2019. This has not yet happened, so we can expect that any day now the changes will come;
  • Phase 2 changes were proposed for June 2019;
  • Phase 3 changes were schedule for December 2019.

When they do come into effect, they will not affect contracts already entered into. The old Security of Payment Act will still apply to these contracts.

Phase 1: February 2019

Investigation and enforcement powers for the Department

The most wide-reaching changes concern new powers of officers of the Department of Finance, Services and Innovation that can be used for the purposes of investigating, monitoring and enforcing compliance with the Security of Payment Act.

Authorised officers may now:

  • Require a person to provide them with information or records that they can obtain;
  • Require a person to answer questions on topics about which they are suspected of having knowledge, or to attend at a specified time and place to answer such questions;
  • Enter premises (including commercial premises without a search warrant);
  • When entering premises, make examinations, direct persons to produce records for examination, copy records, and seize anything suspected on reasonable grounds of being connected with an offence under the Security of Payment Act.

The Amendment Act also introduces offences for failing to comply with the above without reasonable excuse, or obstructing or delaying an authorised officer. The maximum penalty is $4,400 for a corporation and $2,200 for an individual.

There are even greater maximum penalties for providing information, answers or records that are false or misleading: $55,000 for a corporation and $11,000 for an individual.

Authorised officers will also be able to issue quick penalty notices for more minor infringements to the Security of Payment Act.

Liability of directors and managers

The Security of Payment Act already provides for offences of a corporation. See the next section for examples.

The Amendment Act now extends this liability to its directors, or for those involved in the management of the corporation (managers).

Where

  1. A corporation commits an offence against the Security of Payment Act, and
  2. A director or manager aids, abets, induces, conspires, is knowingly concerned in, or is a party to this offence,

then the director or manager will have committed an offence, which is subject to the same maximum penalty as applies to the corporation.

The Security of Payment Act also creates an “executive liability offence”. This is an offence involving specifically the supporting statement to a payment claim. These statements are required to be put forward by head contractors to certify that subcontractors have been paid.

Where:

  1. A corporation fails to attach a supporting statement to a payment claim, or the statement provided is false or misleading, and
  2. The director or manager knows this or is recklessly indifferent about it, and
  3. The director or manager has failed to take reasonable steps to prevent the offence.

the director or manager will have committed an executive liability offence. The maximum penalty is $22,000.

One example of failing to take reasonable steps under (3) is failing to ensure that a corporation’s employees, agents and contractors have supervision, and information and training about complying with the Security of Payment Act.

Higher penalties

Head contractors should take note that failure to include a supporting statement not only risks the payment claim to a principal being rendered invalid (which is the current law). Failure to include this is also now subject to tougher maximum penalties: $110,000 for corporations and $22,000 for individuals.

The same maximum penalties now apply where the supporting statement is provided by someone who knows that it contains false or misleading information. As mentioned, directors and managers may also be liable.

There are also offences relating to payment withholding requests. Currently a claimant in an adjudication application can issue a payment withholding request to the principal contractor, requiring them to hold back any money due to the respondent to cover a successful adjudication application. If a person receives this payment withholding request but is not, or is no longer, the principal contract, they must notify the claimant of this fact within 10 business days. The Amendment Act makes the penalties harsher: the maximum penalty for failing to do this is $5,500 for a corporation, and $1,100 for an individual.

There are similar increases in penalties where a claimant withdraws an adjudication application but fails to tell a principal who has received a payment withholding request, and where a respondent fails to comply with the direction by an adjudicator to give the identity and contact details of a principal contractor.

Adjudications reviewable for error

The Amendment Act now puts into writing what the courts have already decided. This is that an adjudicator’s determination, or any part of it, that is affected by jurisdictional error may be set aside by the Supreme Court. A jurisdictional error is where an adjudicator wrongfully decides a case that it has no authority to decide under the Security of Payment Act, such as where a payment claim is not properly served on the respondent or it is served without a supporting statement.

However, non-jurisdictional error, such as where an adjudicator makes a mistake about what the law is, is not reviewable.

No ball for companies in liquidation

A new change is that if a corporation claiming progress payments enters liquidation at any stage up until the final determination by an adjudicator, it will be prevented from claiming.

The NSW government is now denying the right of a corporation which is in liquidation to serve a payment claim, and is not allowing them to enforce a payment claim such as through applying for adjudication under the Security of Payment Act. This overrides some of a recent NSW Court of Appeal judgement.

A corporation that goes into liquidation while a determination is being considered is taken to have withdrawn the application.

There are uncertainties that NSW courts may need to resolve. Firstly, it appears that notwithstanding these changes, claimants in liquidation may still use the alternative to adjudication, which is enforcing a statutory debt that arises from unpaid payment schedules. Secondly, the Amendment Act does not appear to affect companies in voluntary administration. However, we may know for sure when the courts address these questions.

Phase 2: June 2019

Reference dates are no more

The Amendment Act removes the reference date system that has been the bane of many a claim.

It appears that the entitlement to a progress claim is no longer triggered by a reference date, but is merely triggered by that party undertaking to carry out construction work.

Under the new changes, contractors may serve a payment claim “on and from the last day” of the month in which work was carried out. If the contract provides for an earlier date of any month, the contractor may serve the payment claim from that date.

Only one payment claim per month

Unless the contract says otherwise, a claimant can only serve one payment claim in any particular month for work carried out in that month (previously one claim per reference date).

Parties can still include in a payment claim amounts that were the subject of previous payment claims, or include claims for work completed in previous months.

Payment claims after termination

Where a contract has been terminated, a contractor may serve a payment claim on or after the date of termination. This is a change from the existing law.

Endorsement of payment claims

In a return to the previous law, payment claims to be valid must state that they are “made under the Building and Construction Industry Security of Payment Act 1999”.

Shorter deadline for subcontractor payments

Where a party receives a payment claim from a subcontractor, the payment is due 20 business days after the payment claim is made (previously: 30 business days). If the contract provides for a shorter deadline, this shorter deadline will apply.

Withdrawal of an adjudication application

A claimant may now withdraw its adjudication application at any time before the application is determined. It can do this by serving written notice on both the respondent and the adjudicating body (and on the adjudicator, if one has been appointed).

Extended time for adjudicator’s decision

Under the original Security of Payment Act, the adjudicator must decide the application within 10 business days after notifying both parties that it has accepted the application.

The Amendment Act changes this where the respondent is entitled to lodge a response (e.g. where it had issued a payment schedule). The deadline for deciding the application is 10 business days after the respondent has lodged the response. If no response is lodged, the 10 business days start ticking at the end of the period that the respondent could have issued a response.

The adjudicator must now serve the determination on the claimant and the respondent.

Phase 3: December 2019

Owner-occupier exceptions removed

The Amendment Act makes changes so that the Security of Payment Act will apply to residential construction contracts between a builder and an owner-occupier of the building (that is, someone who resides or proposes to reside in the building).  Currently the Security of Payment Act does not apply to these contracts.

Codes of practice

The Minister for Innovation and Better Regulation may now prescribe a code of practice for adjudication bodies to follow. They will publish this on the NSW legislation website.

Bonus phase: May 2019

Lastly, Fair Trading NSW is also proposing changes to the Building and Construction Industry Security of Payment Regulation 2008 (Regulations).

These changes are scheduled to be drafted by May 2019, at which point stakeholders will be able to submit comments on these proposed changes.

  • Retention moneys for projects valued at over $20 million must currently be held in a trust account. It is proposed to reduce this threshold to $10 million, and to reduce annual reporting obligations on this trust account.
  • Fair Trading NSW proposes to amend the Regulations to require the keeping of trust account records by a head contractor, and to allow subcontractors to inspect these records if they have their retention held.
  • Liability of directors and managers of companies is proposed, for offences under the Regulations. These mainly relate to head contractors and trust accounts.

Conclusion

Fair Trading NSW has recommended that these changes be staggered over the course of a year to allow people in the industry to prepare for them. It is vital that everyone involved in construction and building business familiarise themselves with them. Even tiny non-compliances may have big consequences for adjudications. They can also give rise to criminal liability and severe penalties.

Businesses also need to be aware that authorised government officers will soon be perfectly within their rights to demand access to their documents and premises, and to demand answers to questions in relation to Security of Payment Act issues.

If you or someone you know wants more information or needs help or advice, please contact us on +61 (0)2 9248 3450 or email [email protected].