Tag Archive for: SOPA

AMENDMENTS MADE TO THE SECURITY OF PAYMENT REGIME IN NSW – WHAT BUILDERS NEED TO KNOW

Further reforms to the Building and Construction Industry Security for Payment Act 1999 (NSW) (the Act) have been proposed with the Building and Construction Legislation Amendment Bill 2022 (the Bill) and in the Building and Construction Legislation Amendment Regulation 2022 (the Regulation). The Bill outlines various proposed amendments in relation to the role of adjudicators, the threshold of value of projects when triggering retention funds, and regarding the process of serving payment claims.

Proposed Amendments

The following are the key proposed amendments:

  • The introduction of an ‘adjudication review model’ will allow claimants and respondents to request a review of an adjudication determination.
  • There will be a significant reduction in the threshold of the value of projects in triggering retention funds from $20 million to $10 million.
  • Payment claims which are served on owner occupiers will need to attach a Homeowners Notice information to the payment claim to ensure homeowners understand the SOPA provisions relating to payment claims and to outline the consequences of non-compliance.
  • Increasing the powers of adjudicators in engaging experts to investigate aspects relevant to the adjudication.

Adjudication Review Model

The adjudication review model will allow claimants and respondents to request a review of an adjudication determination.

However, there will be some restrictions in applying for a review of a determination. The determined amount must be:

  • Equal or greater than $100,000 of the scheduled amount; or
  • Less than $100,000 of the claimed amount.

While this amendment will allow parties to have a determination reviewed in specific circumstances, it will also add a layer of extra time and cost to the adjudication process. This is despite security of payment processes generally being considered a timely and less expensive means to resolve payment claim disputes.

Decrease in Threshold When Triggering a Retention Fund

The threshold of the value of a project which requires a retention fund will be reduced from $20 million to $10 million. This will allow for greater protection of retention funds held for the benefit of subcontractors, especially in circumstances where the head contractor becomes insolvent.

New Requirements for Payment Claims

The Bill has proposed changes with respect to the issuing of payment claims to homeowners, with the new requirement that there be a Homeowners Notice enclosed.

The Homeowners Notice will include information regarding the reason that the payment claim is being issued, the correct procedure in responding to the payment claim, and the consequences of disregarding the payment claim.

The Homeowners Notice has been proposed due to the level of uncertainty among homeowners who are unfamiliar with the security of payment regime. It is inferred that issuing a Homeowners Notice will allow homeowners to adequately understand the procedure under the security of payment regime and respond appropriately.

Strengthening the Powers of Adjudicators

The Bill endeavours to afford adjudicators further power in settling disputes. In brief, the powers will extend to adjudicators engaging an independent expert to investigate the relevant works and provide a report indicating their findings.

To Consider

In light of the proposed amendments to the security of payment regime, it is crucial that those who are involved in the construction industry are aware of the proposed changes and, if implemented, take note of the date the legislation will be in effect.

Please click the following link to access the Bill and Regulation:

Regulations link

Bill link

WESTERN AUSTRALIA LEGISLATIVE REFORMS FOR SECURITY OF PAYMENT- THE BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2021 (WA)

OVERVIEW

The Building and Construction Industry (Security of Payment) Act 2021 (WA) (the “new Act”) will introduce new security of payment laws that aim to provide a higher level of protection for contractors in recovering payments.

The first stage of reforms will take effect on 1 August 2022 and the following stages will be effective from 1 February 2023 (Stage 2) and 1 February 2024 (Stage 3). It is important to note that all construction contracts entered into prior to 1 August 2022 will continue to be subject to the Construction Contracts Act 2004 which, as of the date of enforcement, will be referred to as the Construction Contracts (Former Provisions) Act 2004.

CHANGES TO BE IMPLEMENTED

The new Act introduces additional rights to payment under construction contracts and further avenues to recover payments owed to contractors.

The changes to be implemented include but are not limited to:

New Security of Payment Laws

  • Payment timeframes where a payment claim is made will be shortened to 20 business days for the head contractor on a project, 25 business days for subcontractors, and 10 business days for certain types of home building works;
  • If no payment schedule is provided, the respondent is required to pay the amount claimed and will be unable to respond to any application for adjudication;
  • A rapid adjudication process will be implemented with the time period for bringing an adjudication application being reduced from 90 to 20 business days;
  • There will be a prohibition of certain contract terms including “pay when paid” and unfair time bars; and
  • There will be a right to suspend work for reasons of non-payment of progress claims.

Retention Trust Scheme

A retention trust scheme will now apply to construction contracts valued over $1 million and the minimum contract value for the scheme to be applicable will be lowered to contracts over $20,000 (by regulations).

To protect retention money in the event of insolvency, the money held or withheld under a construction contract will be held in trust for the benefit of the party who provided the money.

Expanding the Powers of Building Industry Regulators

Building industry regulators will now have the authority to exclude persons with a history of financial failure from the registered building contractor market. This is to prevent persons from contracting with incompetent or predatory businesses.

Further, persons who exercise intimidation or threatening behaviour to prevent another from exercising their rights under the new Act may be prosecuted.

 

TO CONSIDER

With the introduction of legislative reforms with regards to security of payment in Western Australia, it is essential for contractors to become familiar with the additional rights that arise under the new Act, and for principals to be aware of the importance of providing a valid payment schedule when served a payment claim and managing their finances accordingly.

If you require further information, please see the Action Plan for Reform dated September 2021 and issued by the Department of Mines, Industry Regulation and Safety, or contact our office to speak to one of our lawyers to discuss how the new Act will apply to your construction contract.

 

The Importance of Distinguishing Domestic Works in Construction Contracts- Applying the Victorian Security of Payment Act to Contracts for Mixed-Use Developments

Overview

The application of the Building and Construction Industry Security of Payment Act 2002 (SOP Act) and the Domestic Building Contracts Act 1995 (DBC Act) were considered in the recent decision in Piastrino v Seascape Constructions Pty Ltd [2022] VSC 20, which emphasises the importance of avoiding ambiguity when drafting contracts, particularly when it involves domestic building work or mixed-use development projects. Clear drafting can protect builders under the SOP Act and limit the likelihood of the contract being excluded under the Act as “domestic building” works.

The Facts

A construction contract was entered into between Seascape Constructions (Builder) and Mr and Mrs Piastrino (Owners). It was agreed that the following works were to be completed:

  1. The construction of four apartments;
  2. Modifications to be made to a hair salon; and
  • The installation of a car stacker.

Following a dispute between the Builder and the Owners, the Builder issued an Adjudication Application under the SOP Act.

The Owners disputed this application on the basis that the SOP Act excludes domestic building contracts as per section 7(2)(b) which provides that the Act does not apply to:

a construction contract which is a domestic building contract within the meaning of the Domestic Building Contracts Act 1995 between a builder and a building owner (within the meaning of that Act), for the carrying out of domestic building work (within the meaning of that Act), other than a contract where the building owner is in the business of building residences and the contract is entered into in the course of, or in connection with, that business.

The determination concluded that the SOP Act did in fact apply and that the adjudicator therefore had jurisdiction to issue a determination under the SOP Act.  The adjudicator’s reasoning included consideration that the Owners were in the business of building residences and that the above exception applied.  The Owners applied to the Court for a certiorari to override the adjudicator’s determination.

Proceedings

Three questions arose when the Court considered whether the exclusion in section 7(2)(b) applied in the above-mentioned circumstances.

Mixed-Used Developments and Domestic Building Work

The first question was whether the exception under section 7(2)(b) regarding mixed-use developments applied. Namely, if there was domestic building work in addition to work of a different nature that had been distinguished in the contract.

Under section 12(2) of the DBC Act, a builder is only entitled to payment for carrying out domestic building work if the builder clearly identifies and distinguishes:

(a) the domestic building work from the other work or reason; and

(b) the amount of money the builder is to receive under the contract as a result of carrying out the     domestic building work from the amount of money the builder is to receive under the contract as a result of carrying out the other work or for the other reason.

It was found that the Contract did not distinguish the domestic building work from any other kind of work.

As a result, the Court applied the “dominant character” test in determining whether the construction works under the Contract were considered domestic building work, upon which the SOP Act would apply to the entirety of the contract. As the Contract involved the construction of apartments, the Court held that the dominant character of work was that of domestic building work, meaning that the exclusion under section 7(2)(b) could potentially be applicable to the contract as a whole.

The Business of Building Residences

Although the Owners had a minor victory in relation to the first question with the Court concluding that the building works were not considered “mixed-use developments”, it was held that despite this, the Owners were in the business of building residences and that the construction contract was entered into in connection with that business. Though the Owners had not previously engaged in the business of building residences, their initial intention of entering into the Contract for the purposes of contracting and leasing the apartments for profit in the future was found to be in the course of business. It was further found that the commercial scale and nature of the project to redevelop the property and the long-term objective of holding the property as an investment aligned with the scope in relation of business of building residences.

Accordingly, the section 7(2)(b) exclusion of the SOP Act did not operate in the favour of the Owners and the application for certiorari to quash the adjudication determination was denied.

 

To Consider

As highlighted in this matter, it is crucial that builders distinguish “domestic building work” as required under the DBC Act. This is to avoid a potential fine under the act, in addition to preventing pecuniary losses in circumstances where the “dominant character” of the work is found to be domestic building work, the consequences of which would potentially lead to the construction contract, as a whole, being excluded from section 7(2)(b) of the SOP Act. Likewise, even when carrying out domestic building work, it is important for principals to consider the nature of the construction contract at hand and be aware that the SOP Act could potentially apply to the project.

Security Of Payment Reminder: Christmas Is Coming, But Adjudicator Shopping Is Not Permitted

The Building and Construction Industry Security of Payment Act (NSW) (‘SOPA’) is touted as establishing a scheme of “pay now, argue later” which promotes the speedy payment of progress claims and resolution of disputes. While these objects do not prevent parties from serving multiple payment claims in respect of the same amount,[1] they do dictate that parties will not be permitted to reagitate the same issues at multiple adjudications. It is necessary to examine the circumstances in which a previous adjudicator’s finding will be binding in a subsequent adjudication.

 

Section 22(4) of SOPA

Section 22(4) of the SOPA provides a helpful starting point for this analysis. This section provides that where one adjudicator has determined the value of any construction work or of any related goods or services under a construction contract, an adjudicator in a subsequent adjudication must give the work (or goods or services) the same value as previously determined, unless satisfied that the value has since changed.

 

Back in 2009, the New South Wales Court of Appeal considered the effect of section 22(4) of the SOPA in the decision of Dualcorp Pty Ltd v Remo Constructions Pty Ltd.[2] Macfarlan JA held that section 22(4) is not an exhaustive statement of the matters determined by an earlier adjudication which are binding on a subsequent adjudicator. His Honour held that the Act as a whole “manifests an intention to preclude reagitation of the same issues”.[3]

 

Objects of SOPA

Section 3 of the SOPA sets out the objects of the Act: promoting the prompt making and payment of progress claims and speedy resolution of disputes. In Dualcorp, the court held that it would be inconsistent with this objective to allow a claimant who was dissatisfied with the outcome of an adjudication to obtain a fresh reconsideration of its claim by simply serving an identical payment claim. If this were possible, there would be no limit to the number of times a claimant could seek to reagitate the same issues at adjudication.[4] Clearly, such abuse would be inconsistent with the object of the legislation.

 

Did the previous adjudicator determine the merits of the issue?

A claimant will only be barred from reagitating an issue addressed in a previous adjudication where the adjudicator decided the merits of the issue. This point was emphasised by the New South Wales Supreme Court in Arconic Australia Rolled Products Pty Ltd v McMahon Services Australia Pty Ltd.[5] In that case, McMahon made three contentious payment claims describing costs for delay and variations. In a fourth adjudication between the parties, Arconic argued that McMahon was not entitled to reagitate its claim since it had been determined by the previous adjudicator.[6]

 

The Court followed the approach in Dualcorp[7] but clarified that the objects of the SOPA would only be frustrated where the first adjudicator had heard and decided the merits of the claim.[8] Here, the adjudicator had rejected the relevant payment claim as it was made prematurely by McMahon. Given that the adjudicator did not consider the merits of the claim, McMahon was entitled to reagitate the issues raised in that payment claim in a subsequent adjudication.[9]

 

Take home tips

Parties should be wary that they are not entitled to raise the same issues at multiple adjudications.

If you are claimant considering whether to proceed with a second adjudication application, you should carefully consider whether the merits of your claim has been determined by a previous adjudicator.

We can assist with advice regarding a previous adjudication determination and the prospects of seeking a further determination.

[1] SOPA s 13(6).

[2] [2009] NSWCA 69 (‘Dualcorp’).

[3] At [67].

[4] At [52].

[5] [2017] NSWSC 1114.

[6] At [3]–[9].

[7] At [13]–[15].

[8] At [29].

[9] At [31]–[32].

Is a progress certificate issued by the Superintendent (or Architect) a payment schedule for the purposes of security of payment?

It is trite that the “East Coast model” security of payment legislation provides that a respondent in receipt of a payment claim may provide a payment schedule in response[1].  If a respondent fails to provide a payment schedule within the relevant statutory timeframe, generally, the respondent becomes liable to pay the claimed amount[2].

What happens in a case where the contract is administered by a third party – e.g. a project manager, superintendent, architect or quantity surveyor – who provides a progress certificate to one or both parties?  E.g. the superintendent’s certificate under clause 37.2 of an AS4902-2000 or the architect’s certificate under clause N5.1 of the ABIC MW 2018?

Is this certification a payment schedule for the purposes of security of payment?

In our view, the answer will generally be yes.  Below is a summary of some case law in support of our view.

RHG Construction Fitout and Maintenance Pty Ltd v Kangaroo Point Developments MP Property Pty Ltd & Ors [2021] QCA 117 (RHG Constructions)

In RHG Construction, the Queensland Court of Appeal considered an amended AS4902-2000 contract and whether or not the provision of a payment certificate by the superintendent was a payment schedule under the Building Industry Fairness (Security of Payment) Act 2017 (BIFA).

Clause 37.2 of that contract was in generally standard form terms, requiring the superintendent to receive payment claims and issue to the principal and contractor:

“a certificate evidencing the Superintendent’s assessment of retention moneys and moneys due from the Contractor to the Principal pursuant to the Contract.”

Clause 37.2 of the contract contained the following paragraphs included by way of amendment to the AS4902-2000 standard drafting (Deeming Clause):

“In so far as necessary to ensure compliance with the Security of Payment Act, the Superintendent is deemed to issue any payment schedule under clause 37.2 or final payment schedule under clause 37.4 as the agent of the Principal and each such schedule shall constitute a payment schedule for the purposes of the Security of Payment Act.

For the purposes of and where permitted by the Security of Payment Act, each of the dates for delivery of a payment claim in subclause 37.1 constitutes a reference date.”

The contractor issued a payment claim and the superintendent issued an assessment within the relevant statutory timeframe[3].  The assessment stated (relevantly):

“This Payment Schedule has been produced pursuant to the Works Contract for the residential flat being constructed at 98 River Terrace, Kangaroo Point, between the Principal ‘Kangaroo Point Developments MP Property Pty Ltd’ and the Contractor ‘RHG Contractors Pty Ltd’. This Payment Schedule confirms that the Superintendent has assessed, calculated and certified the proper value of Work Under the Contract.”[4]

A week later, the principal’s solicitors issued correspondence enclosing a further purported “payment schedule” to the contractor denying the validity of the payment claim and stressing that if it was incorrect on that point, the document under the correspondence was to be taken to be the principal’s payment schedule for the purposes of the BIFA[5].

The contractor proceeded to adjudication citing the superintendent’s assessment as the principal’s payment schedule under the BIFA and the adjudicator agreed[6].  The principal applied to court for an order declaring the adjudicator’s determination void.

At first instance, Dalton J agreed with the principal that (notwithstanding the Deeming Clause) the superintendent’s assessment was not a payment schedule and ordered the adjudicator’s determination void.  Her Honour considered that the assessment did not comply with s 69(b) of the BIFA because it was a recommendation only as to payment and the document failed to state “the amount of the payment, if any, the respondent proposes to make”, as required by the BIFA[7].

The Queensland appellate court (Sofronoff P, wth McMurdo and Mullins JJA agreeing) overturned the trial judge’s order.  Sofronoff P said the following as to the standard form clause 37.2:

“For many years now, those engaged in construction have employed the standard form contracts drafted by a committee of Standards Australia, a not-for-profit company which, among other things, prepares draft general conditions of contract for various kinds of commercial transactions… Clause 37, which deals with progress claims, as been in its current form since 2004 when the Act of that year was passed.  It has been the subject of much academic analysis and has doubtless been relied upon by commercial parties thousands of times since then.  The effectiveness of clause 37.2 to engage the adjudication provisions of the 2004 Act, and now the current Act, has never been called into question.[8] (emphasis added)

The effect of the issue of the certificate by the superintendent was the triggering of the principal’s obligation to pay.  Accordingly, the certificate does meet the requirement of s 69(b) of the BIFA[9].

The Deeming Clause was, therefore, “neither artificial nor contrived” [10].  The court considered it relevant that there was no other contractual mechanism whereby a payment schedule would be provided[11].  It would be commercially unworkable for the principal and the superintendent to each issue payment schedules (i.e. one for the purposes of statute and one for the purposes of the contract) because they may differ materially (e.g. provide a vastly differing scheduled amount) [12].

Bucklands Convalescent Hospital v Taylor Projects Group [2007] NSWSC 1514 (Bucklands)

We are not sure whether Sofronoff P’s comment that the effectiveness of clause 37.2 of the Australian Standard contract had never been called into question considered authorities from other east coast jurisdictions.

For example, in Bucklands, Hammerschlag J considered the effectiveness under the NSW statute of clause 37.2 of the AS4000-1997, which provides for the same mechanism of superintendent assessment as the AS4902-2000.

While His Honour considered that the question of jurisdiction should be determined by the adjudicator at first instance[13], His Honour[14], noted that a principal may clothe an agent with authority to provide a payment schedule on their behalf for the purposes of the Building and Construction Industry Security of Payment Act 1999 (NSW) (NSW Act).  The requirement for the superintendent to act honestly and impartially in performing certain functions under the contract, including assessing payment claims, is not the issue at hand[15].  The question:

“…is whether in the circumstances Simmat was exercising function under the contract. Whether it was or was not is a matter of fact. As a matter of law it does not seem to me that a person who is a Superintendent under a contract and who has certifying functions under it is incapable of being appointed as agent to respond to a payment claim under the Act.”[16]

The question was not answered in Bucklands as this was the job of the adjudicator.

However, His Honour’s comments suggest that the use of the standard-form contractual mechanism by the superintendent when progress certificates is likely to give rise to an implication that the superintendent had authority to issue a statutory payment schedule and that the payment certificate was indeed to be interpreted as such.  We consider it likely that the courts would continue to take positions on these issues which is facilitates the objects of the legislation, rather than unduly technical interpretations which themselves would prejudice a party.

Take away tips

As:

  1. the agent (e.g. superintendent, architect, quantity surveyor, etc) will usually act as agent of the respondent under the contract for the purposes of issuing progress certificates (even if they must assess payment claims honestly, reasonably, fairly or the like); and
  2. judicial interpretation of the interplay between widely-used standard form contractual mechanisms tends to favour and facilitate commercial workability,

we are of the view that additional drafting of the kind of the “Deeming Clause” in the RHG Constructions case may not necessarily be required to ensure compliance with the legislation and ensure that the respondent’s interests will not be prejudiced[17].  However, if it is omitted, ensuring that the agent’s payment certificate:

  1. states that it is a payment schedule under the relevant legislation; or
  2. annexes a further document provided by the respondent confirming that the superintendent’s assessment of the amount payable should be taken to be the scheduled amount under the legislation,

are prudent steps to take.  It would also be beneficial for the contract or terms of engagement between the agent and the respondent to expressly state that part of the agent’s engagement is to issue payment schedules under the legislation on behalf of the respondent, having regard to Bucklands and the classic agency case Baulderstone Hornibrook Pty Ltd v Queensland Investment Corporation [2007] NSWCA 9.

What to do if you are the respondent party (e.g. the principal or owner) and you disagree with your agent’s assessment of the payment claim?  That will be the subject of one of our next articles!

[1] E.g. see s 14(1) of the NSW Act.

[2] E.g. see s 14(4) of the NSW Act (subject to s 17(2)).

[3] Kangaroo Point Developments MP Property Pty Ltd v RHG Construction Fitout and Maintenance Pty Ltd & Ors [2021] QSC 30 at [5].

[4] Ibid at [13].

[5] Ibid at [6].

[6] Ibid at [19].

[7] Ibid at [14].

[8] RHG Construction Fitout and Maintenance Pty Ltd v Kangaroo Point Developments MP Property Pty Ltd & Ors [2021] QCA 117 at [23].

[9] Ibid at [27].

[10] Ibid.

[11] Ibid at [28].

[12] Ibid.

[13] Bucklands Convalescent Hospital v Taylor Projects Group [2007] NSWSC 1514 at [26].

[14] At [33] referring to Baulderstone Hornibrook Pty Ltd v Queensland Investment Corporation [2007] NSWCA 9.

[15] Ibid at [34].

[16] Ibid at [35].

[17] Assuming the respondent agrees with the superintendent’s assessment.

10 things that residential builders need to get right

1. Contracts – make sure they comply with the requirements under the Home Building Act (HBA)

The contracts should:

• comply with the contract requirements under the HBA if the builder is carrying out work with a value of $5,000 (including GST) and above, for example the contracts should be in writing, provide a sufficient description of the work etc. Its best to use the standard forms as they contain all of the required information;

• not just be a quote or a purchase order as they do not comply with the HBA requirements and the builder will be in breach of the HBA and unable to rely on the quote or purchase order to get paid when contracting directly with a homeowner. Of course, there are exceptions to these requirements in the case of any emergency work concerning a hazard or a safety issue;

• ensure that builders don’t exceed the maximum deposits and maximum progress payments;

• ensure that the works are clearly defined in terms of scope and price and that any ambiguity is resolved before the contract is signed; and

• make it clear that the contract price can change for variations, PC and provisional sums etc.

2. Licencing – don’t carry out any residential building work that the builder is not licenced to do

Builders must ensure:

• that all of its sub-contractors that carry out specialist work (and any sub-contractors that are required to be licenced) such as its water proofers, plumbers and electricians are appropriately licenced;

• that the entity which has entered into the contract with the homeowner is licenced to carry out the work. It is not good enough for a builder to engage a licenced sub-contractor to carry out the work, the entity entering into the contract has to be licenced to carry out the work; and

• that there are no restrictions on the licence if the builder is contracting directly with homeowners. We have seen too many times to count, instances where the entity in the contract does not hold an open licence to carry out the work and has a condition on the licence which says that the entity is not licenced to carry out works for which HBCF insurance is required, that is, work with a value of over $20,000.

3. Insurance – no insurance = big problems

Remember that:

• the entity which is entering into the contract must have its insurance in place including insurance under the Home Building Compensation Fund (HBCF) if the value of the work is $20,000 or over;

• it is a breach of the HBA to take any money from a homeowner (including a deposit) when a certificate of HBCF has not been provided to the homeowner; and

• if HBCF insurance is not in place, the builder is not entitled to make any claims for payment even on a quantum meruit basis, unless the Court or Tribunal considers it “just and equitable” for the builder to recover money in the absence of insurance. Also, if there are defects in the work carried out, it would be much harder to satisfy a Court or Tribunal that the builder should be paid and also, harder to obtain retrospective insurance.

4. Increases in the contract price/variations/PC and provisional sums

• ensure that the builder complies with the variation procedure in the contract.

All variations should be approved in writing by the homeowner including not only the approval to carry out the variation itself but also approval of the cost of the variation. No variations should commence until written approval has been obtained from the homeowner. By taking this simple step will avoid a lot of headaches down the track in terms of getting paid; and

• All PC and provisional sums should be based on firm estimates or quotations to limit any surprise and of course disputes.

5. Quality of sub-contractors – find the good ones

• find good quality sub-contractors and pay them well.

Most defect claims will come down to the quality of the work carried out by the builder’s sub-contractors and so it’s a worthwhile investment to have quality trades carrying out the works.

• good quality water proofers are in hot demand carrying out rectification work and it’s easy to see why given that most defect claims include water ingress issues caused by failed waterproofing in wet areas, balconies and planter boxes [we could have a whole section dedicated to why planter boxes may look good but are a nightmare for builders in terms of defect claims but that’s for another day].

6. Practical Completion – what does it mean?

• clearly define what practical completion is as this can be a point of contention between builders and homeowners as homeowners may be under a misapprehension of what practical completion actually means; and

• as a practical suggestion, ensure that the works are practically complete and all minor defects are rectified before the homeowner inspects as this will help to avoid the common dispute about when PC has been reached and the homeowner withholding the final progress claim because they are unhappy with the works. Remember the homeowner is buying “the dream” and expects that the house will be ready to occupy. It is better in the long run, in terms of cost and time, to try and meet that expectation if possible.

7. OC – clearly specify the builder’s obligations in relation to obtaining the OC?

• clearly specify in the contract what the builder’s obligations are in relation to providing the certificates and documents required in order to obtain the OC (which is usually the homeowner’s responsibility to obtain from Council or a private certifier) and also stipulate whether the builder has an ongoing obligation to assist the homeowner in obtaining the OC.

8. Claims by the builder – have the paperwork in order

• if the builder is making claims for the payment of money due under the contract, ensure that the contractual provisions are complied with concerning the builder’s entitlement to those moneys and that all supporting documentation is provided; and

• ensure that progress claims are not issued prematurely when the work the subject of the claim has not been completed (as this could be deemed to be a breach of the contract and a breach of the HBA).

9. Claims by homeowner – defects/incomplete work/negligence

• use the defences available under the HBA if the builder has been instructed to carry out works by the homeowner or a professional such as an architect or engineer, contrary to the builder’s advice. The builder must put any objection to carrying out any such works in writing to the homeowner;

• use every opportunity to rectify defects to limit the issues in dispute. There is no strategic advantage in delaying rectification in exchange for the payment of money as this will only end up in litigation as builders are liable to fix defects regardless of whether payment has been made; and

• any items not agreed can be resolved with the assistance of NSW Fair Trading, mediation or proceeding to a Court of Tribunal to determine as a last resort.

10. Keep up to date with the changes in legislation

By way of example, some of the recent changes (some of which apply to class 2 buildings only) include:

• From 10 June 2020, owners with defects will benefit from the statutory duty of care that applies to new buildings, and existing buildings where an economic loss first became apparent in the previous 10 years;

• From 1 September 2020, the NSW Building Commissioner will be able to stop an occupation certificate from being issued, order developers to rectify defective buildings, and issue stop work orders;

• From 1 March 2021, residential builders can rely upon the Building and Construction Industry Security of Payment Act (SOPA) and issue payment claims against homeowners. See our attached article here; and
• From 1 July 2021, there will be compulsory registration for practitioners involved in design and building work, including professional engineers

If you would like to discuss any of the above, please contact us.

Attention residential builders in NSW – big changes ahead from 1 March 2021 you will be able to use the Building and Construction Industry Security of Payment Act to recover money owed by homeowners

On 1 September 2020, the NSW Government released the Building and Construction Industry Security of Payment Regulation 2020 (2020 Regulation) which radically changes the way residential builders and homeowners resolve disputes in relation to outstanding progress claims after 1 March 2021.

Currently, section 7(5) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) and section 4(1) of the Act provide that the Act does not apply to owner occupier construction contracts, that is, contracts where the homeowners intend to live in the premises.  In these instances, residential builders cannot use the Act to recover outstanding progress claims due from homeowners.

This will all change on 1 March 2021 when the 2020 Regulation commences which will remove owner occupier construction contracts as a prescribed class to which the Act does not apply.

This means come 1 March 2021, residential builders will have a statutory right to payment and be able to serve payment claims on homeowners under the Act and apply for adjudication in relation to any outstanding progress claims.

This is a big game changer for residential builders as it will improve cash flow and mean that residential builders will be able to claim outstanding progress claims from homeowners without having to get involved in expensive and lengthy Tribunal and Court proceedings in order to get paid.

Whilst homeowners will still be entitled to bring a building claim in the Tribunal or Court for defective work and the like, such a claim will not defeat or delay residential builder’s entitlements under the Act.  This means that homeowners will be required to pay any amount awarded pursuant to an Adjudication Determination prior to the determination of any Tribunal or Court proceedings which will (in most cases) reduce in the issues in dispute in any Tribunal or Court proceedings.

What residential builders need to know now

The NSW Government has given residential builders and homeowners a transition period to adjust to these major reforms.  We suggest during this period residential builders should familiarise themselves with the Act and their contracts in relation to:

  • the requirements of valid payment claims including serving supporting statements with all payment claims where builders contract directly with homeowners;
  • the dates from and methods of service of valid payment claims;
  • identification of a valid payment schedules by homeowners;
  • review of your standard contracts to ensure that they comply with the minimum contracting requirements and minimum variation requirements under the Home Building Act 1989 NSW (HBA), as this may effect how an adjudicator assesses amounts payable under the contract so your paperwork has to be in order;
  • review your practices and procedures to ensure that you have the necessary resources to utilise the adjudication process and respond within the strict time frames. The benefit of this is that it will reduce the time and cost (in most cases) of litigation as an Adjudication Determination will usually be received within 21 days of lodging the Adjudication Application; and
  • get legal advice to set yourself up so you can utilise the Act and put yourself in the best position to get paid.

CONTRACTOR STRIKES SECURITY OF PAYMENT GOLD BY SKIRTING THE MINING EXCEPTION

Mining owners and operators in most Australian States[1] will be aware of the “mining exception” in security of payment legislation.  The mining exception excludes ‘the extraction (whether by underground or surface working) of minerals, including tunnelling or boring, or constructing underground works for that purpose[2] (Mining Exception) from the definition of the term “construction work” and, consequently, the ambit of statutory interim progress payment mechanisms.

However, in a decision handed down on 11 November 2020, the NSW Supreme Court[3] followed the approach of the Queensland courts[4] by construing the Mining Exception narrowly in favour of contractors and subcontractors.  In short, the Mining Exception does not  extend generally to some broad category of mining industry operations.[5]

Facts

Downer EDI Mining Pty Ltd (Downer) was engaged by Cadia Holdings Pty Ltd (Cadia) the operator of the Cadia East underground panel cave mine south-west of Orange, under a “Works Contract” dated 16 November 2018 (Contract), to perform “development phase” works, being (for the most part) underground works to provide access to the proposed undercut and extraction levels for future extraction of minerals in the “production phase”[6]

Downer proceeded to adjudication on a payment claim served on Cadia.  An adjudicator appointed under the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA) determined that Cadia pay Downer $1,017,741.72.[7]

Cadia challenged the determination on two grounds:

  1. the Mining Exception applied so the Contract was not a “construction contract” within the meaning of the SOPA; and
  2. there was no available reference date to support Downer’s payment claim.

Decision

Cadia’s challenge to the adjudication determination was unsuccessful on both grounds.

Stevenson J framed the effect of the Mining Exception as excluding ‘from the definition of “construction work”, the following works:

  • extraction (whether by underground or surface working) of minerals;
  • tunnelling or boring for the purpose of extraction (whether by underground or surface working of minerals; and
  • constructing underground works for the purpose of extraction (whether by underground or surface working) of minerals.[8]

His Honour held that the heart of the question of the application of the Mining Exception to a contract is what a contractor undertakes to do under the contract in question, not what work that contractor actually does[9] (which comes to be answered later).

The works under the Contract did include “tunnelling or boring” as well as “constructing underground works”.  However:

  1. these activities were not for the “purpose of” extraction of minerals; and
  2. the Contract required Downer to undertake work beyond these activities which fell within the meaning of “construction work” or the supply of “related goods and services”.

On considering generally whether activities performed by a contractor are for the “purpose of” extraction of minerals, His Honour:

  1. agreed with Fryberg J in Thiess that the relevant purpose should be decided ‘by reference to what a reasonable person in the position of the parties would conclude as to the object of what purpose of the contract[10];
  2. held that the Mining Exception is to be construed narrowly to benefit the subcontractor[11];
  3. held that a close “proximity” between the act of extraction and the tunnelling and boring or construction of underground works was required (and this was not so in this case, where the extraction phase would not begin until 2022 after subsequent works)[12];
  4. considered that “extraction” does not include work “associated with” or “preparatory to” extraction[13]; and
  5. noted that the SOPA expresses where there is an intention to bring in ancillary activities, which is not the case with the Mining Exception[14].

Further, in this case, His Honour considered that some works under the Contract required of Downer were “construction work” or supply of “related goods and services”, meaning the SOPA applied.  Relevantly, His Honour stated (accepting Downer’s counsel’s submission):

…if there is a contract which contains undertakings to carry out construction work and undertakings to carry out work that it not construction work, the contract remains a construction contract. If a payment claim includes a claim for work that is not construction work, the payment claim is valid, but the adjudicator should not award an amount for work that is not construction work. Thus, the Mining Exception has an important role to play in limiting the amount that the adjudicator should award.[15]

On the reference date point, His Honour determined that there was an available reference date under the Contract for the service of the payment claim.  Most of the points raised were of limited significance for general application.  One point of general interest was that a clause of the Contract required Downer to invoice ‘in respect of the Services performed’ of the proceeding month.[16]  Downer’s works were performed not in the preceding month, but at an earlier time.

His Honour relied on s.13(4) of the SOPA which allows a contractor to serve a payment claim within the period determined under the construction contract or 12 months after construction work to which the claim relates was last carried out.  The payment clause in the Contract attempted to restrict the operation of s.13(4) and was a void provision, by operation of s.34 of the SOPA.

Take Home Tips

Contractors who consider that they are not entitled to have recourse to security of payment legislation simply because they work on a mine site should re-examine closely the terms of their contract.  Can it really be said that the contract works are for the “purpose of” extraction?  Or is there some distance between the works to be performed and the eventual act of extraction?

Perhaps there are portions or stages of works under the contract to which the Mining Exception would apply, but this would not necessarily mean that the entire contract is not a “construction contract” within the meaning of the security of payment legislation.

 

 

[1] Queensland, Victoria, South Australia, Tasmania and the Australian Capital Territory.  However, Western Australia is likely to shortly follow suit once the Building and Construction Industry (Security of Payment) Bill 2020 (WA) passes through Parliament.

[2] Section 5(2) of the Building and Construction Industry (Security of Payment) Act 1999 (NSW).

[3] Cadia Holdings Pty Ltd v Downer EDI Mining Pty Ltd [2020] NSWSC 1588 per Stevenson J.

[4] HM Hire Pty Limited v National Plant and Equipment Pty Ltd [2012] QSC 4 and Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QCA 276 (Thiess)

[5] At [133].

[6] At [92] and [93].

[7] At [3].

[8] At [34].

[9] At [70].

[10] At [96], quoting Fryberg J in Thiess at [76].

[11] At [102]

[12] At [103] and [91].

[13] At [104].

[14] At [105].

[15] At [134].

[16] At [171].

How the new 2020 SOPA Regulation will affect owner occupier construction contracts: the key changes that you need to know

Following our article HERE that summarised the reforms introduced by the Building and Construction Industry Security of Payment Regulation 2020 (NSW) (2020 Regulation), this article explains in detail one of the key reforms.

Reform effecting owner occupier construction contracts

Currently, section 7(5) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) and clause 4(1) of the provide that the Act does not apply to the prescribed class of owner occupier construction contracts.

An owner occupier construction contract is a construction contract for the carrying out of residential building work (as defined in the Home Building Act 1989 (NSW)) on such part of any premises as the party for whom the work is carried out resides or proposes to reside in. Accordingly, for this type of construction contract, builders are not able to apply for adjudication if there is a payment dispute.

This position will change when Schedule 2 of the 2020 Regulation commences on 1 March 2021. Schedule 2 of the 2020 Regulation will omit the current clause 4(1) of the 2020 Regulation and remove owner occupier construction contracts as a prescribed class to which the Act does not apply. The effect of this is will be that the Act will apply to owner occupier construction contracts so that builders will be able to serve payment claims on owner occupiers under the Act and apply for adjudication.

What residential home builders and owner occupiers need to know

While the 2020 Regulation commenced on 1 September 2020 and currently provides that the Act does not apply to owner occupied construction contracts, it seems that the NSW Government has provided residential home builders and owner occupiers with a transition period to adjust to the reform.

The period from now until 1 March 2021 should be utilised to understand how the changes will effect residential home builders and owner occupiers. Importantly, both parties should be aware that:

  • Residential home builders will be able to serve payment claims pursuant to the Act on owner occupiers.
  • Owner occupiers should familiarise themselves with the Act as it will apply to contracts entered into for residential building work at their residence (or proposed residence). Most significantly, owner occupiers should be aware of the requirement to serve a payment schedule within 10 business days after the payment claims is served by the builder if the amount claimed is disputed and will not be paid in full. The consequences of not serving a payment schedule within the timeframe prescribed in the Act are serious and may compromise an owner occupier’s right to participate in an adjudication.
  • The due date for payments will be effected. In accordance with section 11(1C) of the Act, a progress payment becomes due and payable on the date on which the payment becomes due and payable in accordance with the contract or within 10 business days after a payment claim is made (if the contract has no express provision regarding the due date for payment).
  • As the adjudication process is relatively quick and cheap to recover progress payments compared to litigation (in some circumstances), it is likely that adjudication will become a popular method for resolving payment disputes under owner occupier construction contracts.

If you would like to discuss or would like any more information, please contact us at [email protected] or (02) 9248 3450.

 

 

Spring is here and so is the Building and Construction Industry Security of Payment Regulation 2020

On 1 September 2020, the Building and Construction Industry Security of Payment Regulation 2020 commenced (2020 Regulation) repealing the 2008 Regulation.

The 2020 Regulation will provide the legislative support and administrative detail for the operation of the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) as provided by the amendments which commenced on 21 October 2019. These amendments came about to address poor payment practices and the high incidence of insolvencies in the building and construction industry and also, to facilitate prompt payment, preserve cash flow and resolve disputes quickly and efficiently.

The 2020 Regulation is not retrospective and will not apply to contracts entered into prior to its commencement date.

Key reforms of the 2020 Regulation include:

  • removing the annual reporting requirements for trust accounts to NSW Fair Trading,
  • introducing a requirement for head contractors to keep a ledger for retention money held in relation to each subcontractor and provide the subcontractor with a copy of a ledger at least once every 3 months or longer period of 6 months if agreed in writing, and also to provide trust account records to subcontractors if their money is held in trust,
  • supporting statements are only required for subcontractors or suppliers directly engaged by the head contractor,
  • removing owner occupier construction contracts as a prescribed class of construction contract to which the Act does not apply, and
  • introducing qualifications and eligibility requirements for adjudicators to improve the quality of adjudication determinations under the Act.  The eligibility requirements include either a degree or diploma in a relevant specified field with at least 5 years’ experience, or at least 10 years’ experience in a relevant specified field.  The continuing professional development requirements for adjudicators will commence on 1 September 2021.

Of particular note, the project value threshold (value of the head contractor’s contract with the principal) for retention money trust account requirements will not be reduced from $20 million to $10 million as previously foreshadowed. The existing threshold will remain. Perhaps, given the current climate, it was considered too much of an administrative burden on head contractors who are already dealing with the pressures of delivering projects during Covid. A copy of the 2020 Regulation is  here.

If you would like to discuss or would like any more information, please contact us at [email protected] or (02) 9248 3450.

If you would like to receive our regular newsletters, please click  here.